New profiles and major changes

A selected log of verified additions and material project updates. Routine record-date refreshes do not appear here.

New profiles

44 verified log entries

Added to Cartis ·

AirTrunk BOM2 Campus added to Cartis

AirTrunk markets BOM2 in Mahape, Navi Mumbai, Maharashtra with more than 120 MW of total campus capacity. The site is part of its Indian platform following the Lumina acquisition. Public specifications describe power and connectivity, but do not establish how much capacity is commissioned or explicitly define the MW figure as IT load.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

AirTrunk HYD1 Campus added to Cartis

AirTrunk markets HYD1 in Chandanvelly, Hyderabad, Telangana with more than 243 MW of total campus capacity. The site is part of its Indian platform following the Lumina acquisition. Public specifications describe power and connectivity, but do not establish how much capacity is commissioned or explicitly define the MW figure as IT load.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

AirTrunk MAA1 Campus added to Cartis

AirTrunk markets MAA1 in Ambattur, Chennai, Tamil Nadu with more than 128 MW of total campus capacity. The site is part of its Indian platform following the Lumina acquisition. Public specifications describe power and connectivity, but do not establish how much capacity is commissioned or explicitly define the MW figure as IT load.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

Aligned Hillsboro Campus added to Cartis

Aligned Hillsboro Campus. NE 30th Avenue / NE Evergreen Road; 27.02-acre plan. City DR-021-23 lists tax lots 1N220D000300/400 and 1N2210001801/1802/1804. 108 MW planned critical capacity: 72 MW first building plus 36 MW second. Separate 120 MW utility capacity. Operating load unknown. Development approved; current portfolio markets PDX-01 but does not establish full-campus commissioning.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

Ark Hilfield Park Campus added to Cartis

Ark proposes Hilfield Park on the former Mercure Hotel site at Tylers Way. The operator markets approximately 200 MW of compute capacity, with power delivery from 2028 and service targeted for 2029. The campus remains a development proposal; its 250 MVA supply figure is not IT capacity.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

CloudHQ GRU Campus added to Cartis

CloudHQ GRU Campus. Paulínia in Campinas region; operator point -22.77089,-47.10425 identifies campus. Surveyed parcel boundary not recovered. 288 MW full-build critical IT, comprising two phases of three 48 MW buildings each. Operating capacity unknown. Development with transmission licensing activity confirmed; this bundle does not independently establish commissioned data halls.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

CloudHQ MDC Campus added to Cartis

CloudHQ MDC Campus. South of Routes 28/234, operator coordinates 38.73088,-77.50829. Street/parcel boundary not independently recovered. 300 MW planned critical IT campus capacity. OCI describes three 84 MW structures (252 MW construction program); do not represent these different scopes as 300 MW operating. Under construction: OCI reports active on-site quality work from early 2026.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

Digital Connexion Chennai Campus / MAA10 added to Cartis

Digital Connexion’s Chennai campus in Ambattur is planned for four buildings and expansion to 100 MW. Its initial MAA10 facility, launched in January 2024, is specified at 20 MW IT. A DE-CIX presence adds interconnection options; the campus maximum is not its present operating load.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

EdgeConneX Austin AUS01–04 Cedar Creek Campus added to Cartis

EdgeConneX Austin AUS01–04 Cedar Creek Campus. 6752 FM535, Cedar Creek 78612; operator describes 130 acres. AUS02 registration also uses 8001 Wolf Lane Building 2. 336 MW initial campus potential: 96 MW first building, then 48+96+96 MW. Source says power, not explicitly critical IT; do not relabel. Under development; operator first-phase target 2027.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

maincubes mainHub Berlin Campus / BER02 added to Cartis

maincubes is developing mainHub Berlin in Nauen, with BER02 as its first data center. Campus IT capacity is designed to range from 144 to 186 MW depending on configuration. Power infrastructure is under construction, including a substation whose structure was completed in October 2026; service is targeted for Q3 2028.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

Menlo Digital MD-PHX1 Phoenix Campus added to Cartis

Menlo Digital MD-PHX1 Phoenix Campus. 4801–4811 East Thistle Landing Drive, Phoenix 85044; 38.3 acres. 180 MW planned critical IT, separate from 257 MW utility feed. Five two-story buildings; ten 8 MW and ten 10 MW halls. In development; substation/shell targeted Q4 2026, data halls Q1 2027. Targets do not establish completion.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

NTT Dallas Garland Campus added to Cartis

NTT Dallas Garland Campus. TX1: 2008 Lookout Drive; TX4: 2060 Lookout Drive, Garland 75044. TDLR uses campus address 2008 for TX4. 124 MW planned campus IT; TX1 offers 16 MW and TX4 planned 36 MW. Do not label the full campus operating. Partly operational with expansion. TX1 serves customers; TX4 page still uses a June 2026 future availability target, not a commissioning receipt.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

NTT Hillsboro Campus added to Cartis

NTT Hillsboro Campus. HI1 anchor: 4050 NE Evergreen Road, Hillsboro 97124; operator describes a 47-acre campus. 126 MW planned campus IT across five centers; HI1 36 MW critical IT. Actual energized aggregate remains unknown. Partly operational: operator records campus opening in 2020/21 and currently markets HI1. No proof all planned buildings are operating.

The Cartis addition date is not the date the facility opened or was announced.

Added to Cartis ·

Polarnode Keminmaa Sarvenmaa added to Cartis

Polarnode’s Sarvenmaa campus proposal in Keminmaa is undergoing environmental assessment. The operator markets more than 500 MW of grid capacity, while the assessment examines a larger scenario of approximately 1000 MW peak demand. Neither figure describes operating IT load.

The Cartis addition date is not the date the facility opened or was announced.

Major changes

3 verified log entries

Change recorded in Cartis ·

Oxagon construction and first-phase scope updated

DataVolt reported construction underway on a 360 MW first phase, including a planned 100 MW HUMAIN tranche anticipated in 2028. The first phase differs from an older 300 MW report and is not operating capacity.

Recorded status change: No prior recorded status → Construction

Source announcement: . This is distinct from when Cartis recorded the change.

For supporting research and citations, open a project’s evidence page. Read the methodology.