Data center siteSite record

Meta Kuna Data Center

Kuna, Idaho, United StatesUnder construction
Capacity
No public figure
Lead participant
rPlus Energies
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Meta Kuna Data Center

Meta's Kuna campus is an AI-oriented construction project supported by new renewable and municipal water infrastructure. Meta Kuna Data Center is located in Kuna, ID, US and is a data center campus in construction status. Participants include Meta Platforms, Inc. as owner, Meta Platforms, Inc. as operator, Hensel Phelps as contractor, Idaho Power as utility. Development comprises Initial H-shaped campus build (construction). Key milestones include Meta confirms the Kuna water-system investment and gift (2025-12-17) and Secondary opening expectation remains unconfirmed by Meta (2026-12-31). pleasant valley solar 1 support — 200 MW generation: Green-tariff renewable project supporting Meta; not campus IT capacity. pleasant valley solar 2 ppa — 125 MW generation: Twenty-year external generation PPA with a December 2026 target COD.

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Onsite Generation200 MWReported Rounded · Meta Kuna Data Center
Onsite Generation125 MWReported Rounded · Meta Kuna Data Center

Development

1 phases · 6 milestones
Initial H-shaped campus buildUnder Construction

Two data center buildings, four data halls each, connected by central administration building; building-level capacity undisclosed.

2 buildings

Feb 16, 2022
Meta announces the Kuna data center
Completed
Sep 1, 2022
Idaho Commerce reports the September 2022 groundbreaking schedule
Completed
Oct 12, 2023
Meta reports active construction and AI-oriented design
Completed
Jan 3, 2024
Idaho Power files the 125 MW PVS2 PPA
Completed
Dec 17, 2025
Meta confirms the Kuna water-system investment and gift
Completed
Dec 31, 2026
Secondary opening expectation remains unconfirmed by Meta
Day

Infrastructure

Renewable Energy SupplySecured Or Contracted

200 MW generation

Green-tariff renewable project supporting Meta; not campus IT capacity.

Renewable Energy SupplySecured Or Contracted

125 MW generation

Twenty-year external generation PPA with a December 2026 target COD.

Water SupplyOperational

$70 million plus

Meta-funded system gifted to the city; includes water-reuse infrastructure and is not a data center asset after transfer.

Renewable Energy SupplySecured Or Contracted

Idaho Power green-tariff framework; facility power demand remains confidential.

Project map

0 of 1 project point mapped
Infrastructure facts
4
Mapped records
1
Capacity figures
3

No map point available

Power & interconnection: 3Cooling & water: 1

Facts & sources

Published claims and their source links.

22 facts
Current Status
Construction
Actual
First Party Opening Verified
False
Actual
Announced Floor Area
960,000 square feet plus
Reported Rounded
Announced Investment
$800 million plus
Reported Rounded
Future Operational Jobs
100 jobs approximately
Reported Rounded
Peak Construction Jobs
1,200 jobs
Reported Rounded
Initial Building Count
2 data-center buildings
Reported Rounded
Data Halls Per Building
4 data halls
Reported Rounded
Central Administration Connection
True
Actual
Construction Active By
2023-10-12
Actual
Ai Supporting Design
True
Actual
Renewable Generation Project
200 MW generation
Reported Rounded
Pvs2 Generation Ppa
125 MW generation
Reported Rounded
Pvs2 Ppa Term
20 years
Reported Rounded
Water Wastewater Investment
$70 million plus
Reported Rounded
Water System Gifted To City
True
Actual
Water Reuse System
True
Actual
Campus Power Demand Confidential
True
Actual
Campus It Capacity Disclosed
False
Actual
Owner Developer
Meta Platforms
Actual
General Contractor
Hensel Phelps
Actual
Green Tariff Utility
Idaho Power
Actual