Data Tank Utajärvi Campus

Utajärvi, FinlandUnder construction
Evidence
Utility capacity
200 MW
Updated
Oct 29, 2026

Data Tank’s proposed 200 MW Utajärvi campus at Mustikkakangas comprises four planned halls; the capacity basis is not explicitly verified as IT load. October 2026 announcements report preparatory works starting under NYAB, with later phases requiring separate agreements and phased completion targeted by end-2028. The developer reports a binding grid agreement. Permit 26-0014-RL requires acoustic compliance evidence before partial-final or final inspection and a special fire inspection requested before use. Municipal approval of a 26.39-hectare lease arrangement does not establish signature or ownership. The reported €2 billion investment intention is not verified financing.

Capacity

Grid capacity MW

Forecast

200 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Initial site preparationUnder construction

NYAB initial early-works contract, not full hall completion. Evidence: SRC-N220-DATA-TANK-UTAJARVI-U2

Four-hall full buildoutPlanned

4 buildings

Full 200 MW development remains subject to separate future works agreements. Evidence: SRC-N220-DATA-TANK-UTAJARVI-U1; SRC-N220-DATA-TANK-UTAJARVI-U2

Milestones (5)
Municipal board approved original 10 ha lease, recounted in February 2026 decision.

Apr 8, 2025 · Recorded actual event

Completed · Announced

Sources (1)
Board approved additional 10 ha lease, recounted in February 2026 decision.

Oct 14, 2025 · Recorded actual event

Completed · Announced

Sources (1)
Board approved replacement 26.39 ha use/lease agreement; signature not verified.

Feb 3, 2026 · Recorded actual event

Completed · Announced

Sources (1)
Developer announced 200 MW project and power/permit claims.

Jun 11, 2026 · Recorded actual event

Completed · Announced

Sources (1)
NYAB announced immediate first-stage early works; later work requires separate agreements.

Oct 9, 2026 · Recorded actual event

Completed · Announced

Sources (1)

Participants

Data Tank Nordic Oy

Developer

Sources by role
Developer (1)

Site & development

Site location

Reported rounded

Mustikkakangas industrial area, approximately60 km from Oulu; four proposed halls form one campus.

Source

Land and site control context

Reported rounded

February 2026 municipal decision approves a replacement use/lease agreement for 26.39 ha TIETOMAA parcel 889-407-4-131, replacing earlier leased areas. Approval is not proof of contract signature or freehold ownership.

Source

Land transaction market terms

Reported rounded

Council states market terms assessment found no economic advantage in this specific use/lease transaction.

Source

Additional project facts

Reviewed ut works scope context

Reported rounded

The municipality’s October 9, 2026 reproduction of NYAB’s announcement reports a signed agreement with NYAB Finland Oy for first stage site preparation and infrastructure works, with options to expand preparatory works. Work was to start immediately; contract value was undisclosed. NYAB’s involvement in later implementation phases remained under negotiation and required separate agreements—not a whole campus general contractor award. An October 15, 2026 municipal update reports that construction works had begun and gives phased completion by the end of 2028 as a target. Read alongside the October 9 announcement, the verified signed contract scope is preparatory and infrastructure works; the update does not establish completed halls, energized service or contracted later phases.

Source

Reviewed ut permit conditions context

Reported rounded

Permit 26-0014-RL requires a measurement report by an independent qualified acoustics professional demonstrating compliance with the stated maximum 45 dB average sound level criterion, submitted with a compliance statement before partial final or final inspection. A special fire inspection must also be requested before use. These are permit conditions, not evidence that tests or inspections passed; no measurement duration or location is inferred. Permit 26-0014-RL requires commencement within three years and completion within five years of its becoming legally final, subject to extensions. The exact finality date is not established here, so no calendar expiry date is inferred.

Source

Infrastructure & permits

Technical details (3)
Utility service

Reported context

Developer reports binding grid agreement; do not add separate battery MW to data center capacity.

Cooling system

Reported context

Project engineer describes hybrid air and liquid cooling for data halls, with large condensers considered in noise modelling. Installed performance and measured PUE remain unverified.

Water supply

Reported context

Engineering design includes a water reservoir and fire-safety pumping station, with stormwater planning near the Oulujoki River. Reservoir is not asserted to be cooling supply; water allocation and consumption remain unknown.

Other · Documented

Data Tank Utajärvi Campus

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.