Scope and capacity

AdaniConneX's Taloja campus is an announced AI data centre development in the Navi Mumbai region. CoreWeave's October 2026 announcement describes three 80 MW buildings, or 240 MW of deployment capacity, with an option for a further 240 MW. The expansion option is not included in the base figure, and the source does not explicitly define the deployment measure as IT load. First-phase availability is targeted for mid-2028, not already achieved. Planned systems include direct liquid cooling in GPU halls and non-evaporative chilled water. The broader Navi Mumbai portfolio is not treated as the same physical campus. Exact land-title details, campus grid allocation, carrier commitments and project-specific funding were not established.

Headline: 240 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Planned campus capacity MW · 240 MW

Planned / design or future potential · AdaniConneX Taloja AI Campus (Project)

Claim 160810 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. CoreWeave Taloja announcement

    CoreWeave · Document date: Oct 6, 2026 · Primary

    Source reference: SRC-8128 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coreweave.com/news/coreweave-enters-india-expanding-ai-cloud-platform-with-adaniconnex

Site location · Named Taloja campus; CoreWeave’s three buildings are a tenant deployment within it, not a separate campus. Exact plot remains undisclosed in reviewed source.

Reported rounded · AdaniConneX Taloja AI Campus (Project)

Claim 160811 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. CoreWeave Taloja announcement

    CoreWeave · Document date: Oct 6, 2026 · Primary

    Source reference: SRC-8128 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coreweave.com/news/coreweave-enters-india-expanding-ai-cloud-platform-with-adaniconnex

Land and site control context · Taloja locality source confirmed; land area/title unknown.

Reported rounded · AdaniConneX Taloja AI Campus (Project)

Claim 160812 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. CoreWeave Taloja announcement

    CoreWeave · Document date: Oct 6, 2026 · Primary

    Source reference: SRC-8128 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coreweave.com/news/coreweave-enters-india-expanding-ai-cloud-platform-with-adaniconnex

Optional expansion capacity MW · 240 MW

Planned / design or future potential · AdaniConneX Taloja AI Campus (Project)

Claim 160813 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. CoreWeave Taloja announcement

    CoreWeave · Document date: Oct 6, 2026 · Primary

    Source reference: SRC-8128 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.coreweave.com/news/coreweave-enters-india-expanding-ai-cloud-platform-with-adaniconnex

Counterparties and capital

AdaniConneX · Developer, Operator · CMP-0461

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.