CDC Eastern Creek Campus

Eastern Creek, New South Wales, AustraliaOperating
Evidence
Planned / design
200 MW
Updated
Oct 29, 2026

CDC operates six data centres at Eastern Creek in western Sydney. The operator reports more than 200 MW of campus capacity without defining it as IT load or occupied demand. SSD-10330-Mod-3 was approved on 8 September 2026 for an 11 kV switch room, a fifth transformer and replacement of transformers 1 and 2. This updates the approval history but does not establish installation or energization. Current operating IT load, registered title and a project-specific financing allocation remain unverified.

Capacity

Reported campus capacity MW

Planned / design or future potential

200 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (3)
Original expansion consent SSD-10330 granted.

Jul 14, 2020 · Recorded actual event

Completed · Announced

Sources (1)
MOD-1 approved changes to buildings 5 and 6.

Apr 17, 2024 · Recorded actual event

Completed · Announced

Sources (1)
MOD-2 approved changes to backup generator configuration and diesel storage.

Mar 6, 2026 · Recorded actual event

Completed · Announced

Sources (1)

Participants

CDC Data Centres

Developer · Operator

Sources by role
Developer / Operator (1)

Site & development

Site location

Reported rounded

17 Roberts Road, Eastern Creek, New South Wales; Lot 2 DP 1159804. Applicant Canberra Data Centres Pty Ltd.

Source

Land and site control context

Reported rounded

Legal parcel is identified in consent; freehold ownership and land area were not established.

Source

Additional project facts

Modification approval

Actual

SSD-10330-Mod-3 was approved on 8 September 2026 for an 11 kV switch room, a fifth transformer and replacement of transformers 1 and 2. Approval does not establish that this equipment has been installed or energized.

Source

Infrastructure & permits

Technical details (2)
Onsite generation

Reported context

Consent requires at least seven minutes of UPS battery support and caps installed backup generation for its development scope at 238 MW. Generator rating is not utility or IT capacity.

Utility service

Reported context

Consent scope requires at least seven minutes of UPS battery support; an approval condition, not proof of tested current performance.

Other · Documented

CDC Eastern Creek Campus

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
CDC Marsden Park Campus

Under construction · Marsden Park, Sydney, New South Wales, Australia

Shared participant: CDC Data Centres · Same market: New South Wales, Australia