maincubes mainHub Berlin Campus / BER02
- Planned critical IT
- 186 MW
- Updated
- Oct 29, 2026
maincubes is developing mainHub Berlin in Nauen, with BER02 as the first building of a campus designed for 144–186 MW of IT capacity. Its reported 200 MW E.DIS connection agreement is separate from the 200 MVA substation rating; energization is unverified. The detailed operator page targets Q3 2028 service, while portfolio wording also retains Q1 2028. Zoning is effective, not blanket building approval. Supplementary water cooling in the December 2024 planning rationale remains unreconciled with the operator’s zero-process-water design claim; neither establishes zero total water consumption.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
First data-centre building of an up-to-six-building campus; separate substation construction does not establish building completion. Evidence: SRC-N220-MAINCUBES-NAUEN-B1
Milestones (5)
Oct 21, 2024 · Recorded actual event
maincubes announced completion of a 14-hectare purchase in Nauen. This is an operator-reported acquisition, not verified current land-register ownership, parcel schedule or purchase price.
Completed · Announced
Sources (1)
- maincubes announces land purchase in Nauen — October 21, 2024 · Oct 21, 2024 · Primary
Jul 2, 2025 · Recorded actual event
Nauen adopted the 6 December 2024 version of Bebauungsplan Rechenzentrum on 25 February 2025. The 2 July 2025 official gazette announced its entry into force. The associated FNP amendment Südliche Erweiterung GE Ost was approved on 6 June 2025 under reference 63.3-01144-25 and became effective with publication. These are zoning instruments, not blanket building or operational approvals.
Completed · Announced
Sources (3)
- Nauen Bebauungsplan Rechenzentrum — executed plan, December 2024 version · Corroborating
- Zoning and grid agreement · Aug 4, 2025 · Primary
- Amtsblatt für die Stadt Nauen — No. 4, July 2, 2025 · Jul 2, 2025 · Corroborating
Aug 4, 2025 · Recorded actual event
Completed · Announced
Sources (1)
- Zoning and grid agreement · Aug 4, 2025 · Primary
Oct 13, 2026 · Recorded actual event
JSM is general contractor for the 110 kV substation and approximately 6 km cable route to Wustermark, not verified campus-wide building contractor. JSM reported the substation structural topping-out on October 13, 2026. In its October 19 release, JSM said building-services installation was scheduled for the end of October, with transformer installation to follow. The release names Lupp as construction partner. The 200 MVA substation rating is not 200 MW commissioned IT or proof of energization.
Completed · Announced
Sources (2)
- Contractor October progress · Oct 19, 2026 · Primary
- Nauen substation and cable-route groundbreaking — March 24, 2026 · Mar 24, 2026 · Corroborating
Q3 2028 · Forecast / planned record
The detailed operator BER02 page gives a Q3 2028 ready-for-service target, while its portfolio page simultaneously retains Q1 2028 text and a Q3 2028 card. These are inconsistent published targets; no confirmed service date, documented delay or supersession sequence is established.
Forecast · Announced
Sources (2)
- maincubes data-center portfolio — published service-target descriptions · Corroborating
- Current campus specifications · Primary
Participants
Developer · Operator
Sources by role
Developer / Operator (1)
- Current campus specifications · Primary
Capital & incentives
Capital claims
Reviewed ber financing context
Reported roundedDTCP's January 13, 2026 platform financing announcement explicitly includes mainHub Berlin development among supported projects. The package comprises €1.775 billion committed facilities plus a €700 million uncommitted accordion across portfolio refinancing and development. No amount is allocated to Nauen in that disclosure.
SourceSite & development
Site location
Reported roundedBerliner Straße, 14641 Nauen; 52.5935000,12.8929999; approximately 137000 sqm. BER02 is the first building of one up to six building campus.
SourceReviewed ber land control context
Reported roundedMaincubes announced completion of a 14-hectare land purchase in Nauen on 21 October 2024. The city identifies AM:PM Grund Alpha GmbH as the development proponent and maincubes as future operator/implementer. This supports an operator reported acquisition, not a verified current land register owner or purchase price.
SourceTechnical specifications
Process water design context
ForecastOperator describes zero process water usage as a campus design feature; total water use, water sourcing, domestic/fire/construction consumption and measured WUE are not established.
SourceCooling and power redundancy design
ForecastOperator specifies n+1 for flexible cooling and power supply topologies, with block, distributed redundant, catcher or N+2C configurations; not all options simultaneously installed or commissioned.
SourceReviewed ber water design conflict context
Reported roundedThe December 2024 planning rationale envisaged supplementary water cooling above approximately 28°C, with final quantities left to building approval. The current operator page instead advertises zero process water usage as a design feature. The relationship between these descriptions is unverified; neither proves installed equipment or zero total site water consumption. The planning rationale’s account of absent potable water and sewer connections is historical, not a current field observation.
SourceReviewed ber power participants and milestone context
Reported roundedJSM is general contractor for the 110 kV substation and approximately 6 km cable route to Wustermark, not verified campus wide building contractor. JSM reported the substation structural topping out on October 13, 2026. In its October 19 release, JSM said building services installation was scheduled for the end of October, with transformer installation to follow. The release names Lupp as construction partner. The 200 MVA substation rating is not 200 MW commissioned IT or proof of energization.
SourceAdditional project facts
Heat reuse design context
ForecastCampus design includes heat recovery for on campus use and intended local district heating; no executed heat offtake agreement or operating delivery is established.
SourceAutonomous operation design upper bound
ForecastOperator advertises up to 48 hours of autonomous operation and priority fuel delivery. This is a design specification, not tested runtime at every load or proof of installed generation.
SourceReviewed ber planning approvals context
Reported roundedNauen adopted the 6 December 2024 version of Bebauungsplan Rechenzentrum on 25 February 2025. The 2 July 2025 official gazette announced its entry into force. The associated FNP amendment Südliche Erweiterung GE Ost was approved on 6 June 2025 under reference 63.3-01144-25 and became effective with publication. These are zoning instruments, not blanket building or operational approvals.
SourceReviewed ber parcel scope context
Reported roundedThe December 2024 rationale defines a 14.6 ha planning area in Gemarkung Nauen, Flur 17: 35, 36, 157, 159, 209, 210, 211, 212 and parts of 46/7, 232 and 233. Proposed replacements 35 → 257/258, 36 → 259/260 and 210 → 255/256 were still awaiting administrative adoption. Road parcels include public ownership; other land is described as privately owned. This is a dated planning boundary, not the purchased parcel schedule.
SourceReviewed ber utility context
Reported roundedThe operator reported a signed 200 MW grid connection agreement with E.DIS in August 2025 and identified E.DIS distribution network supply in March 2026. Contracted connection capacity is separate from 200 MVA equipment and 144–186 MW planned IT. The operator's 2027 supply statement is a dated expectation, not proof of energization.
SourceReviewed ber service target conflict context
Reported roundedThe detailed operator BER02 page gives a Q3 2028 ready for service target, while its portfolio page simultaneously retains Q1 2028 text and a Q3 2028 card. These are inconsistent published targets; no confirmed service date, documented delay or supersession sequence is established.
SourceInfrastructure & permits
Technical details (5)
Reported context
Dedicated substation described as 200 MVA with 110/20 kV transformers; retain MVA separately from grid-contract MW. JSM delivering six-kilometre connection to Wustermark.
Reported context
Air, liquid or hybrid design; PUE <=1.2 target. The December 2024 planning rationale envisaged supplementary water cooling above approximately 28°C, with final quantities left to building approval. The current operator page instead advertises zero process-water usage as a design feature. The relationship between these descriptions is unverified; neither proves installed equipment or zero total site-water consumption. The planning rationale’s account of absent potable-water and sewer connections is historical, not a current field observation.
Reported context
Four carrier entry points specified.
Planned or represented
200 MW
The operator reported a signed 200 MW grid-connection agreement with E.DIS in August 2025 and identified E.DIS distribution-network supply in March 2026. Contracted connection capacity is separate from 200 MVA equipment and 144–186 MW planned IT. The operator's 2027 supply statement is a dated expectation, not proof of energization.
Planned or represented
200 MVA
Dedicated 200 MVA substation specification; separate from 200 MW grid contract.
Project map
Other · Documented
maincubes mainHub Berlin Campus / BER02
Sources (4)
- Nauen Bebauungsplan Rechenzentrum — executed plan, December 2024 version · Corroborating
- Contractor October progress · Oct 19, 2026 · Corroborating
- Zoning and grid agreement · Aug 4, 2025 · Primary
- Amtsblatt für die Stadt Nauen — No. 4, July 2, 2025 · Jul 2, 2025 · Corroborating
Public-source research. Plans may change. See Evidence for sources and qualifications.