maincubes mainHub Berlin Campus / BER02

Nauen, Brandenburg, GermanyUnder construction
Evidence
Planned critical IT
186 MW
Updated
Oct 29, 2026

maincubes is developing mainHub Berlin in Nauen, with BER02 as the first building of a campus designed for 144–186 MW of IT capacity. Its reported 200 MW E.DIS connection agreement is separate from the 200 MVA substation rating; energization is unverified. The detailed operator page targets Q3 2028 service, while portfolio wording also retains Q1 2028. Zoning is effective, not blanket building approval. Supplementary water cooling in the December 2024 planning rationale remains unreconciled with the operator’s zero-process-water design claim; neither establishes zero total water consumption.

Capacity

Target IT capacity MW

Planned / design or future potential

186 MW

Source

Lower design IT capacity MW

Design

144 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

BER02 first buildingPlanned

1 building

First data-centre building of an up-to-six-building campus; separate substation construction does not establish building completion. Evidence: SRC-N220-MAINCUBES-NAUEN-B1

Milestones (5)
Operator announced completion of land purchase

Oct 21, 2024 · Recorded actual event

maincubes announced completion of a 14-hectare purchase in Nauen. This is an operator-reported acquisition, not verified current land-register ownership, parcel schedule or purchase price.

Completed · Announced

Sources (1)
Zoning became legally binding.

Jul 2, 2025 · Recorded actual event

Nauen adopted the 6 December 2024 version of Bebauungsplan Rechenzentrum on 25 February 2025. The 2 July 2025 official gazette announced its entry into force. The associated FNP amendment Südliche Erweiterung GE Ost was approved on 6 June 2025 under reference 63.3-01144-25 and became effective with publication. These are zoning instruments, not blanket building or operational approvals.

Completed · Announced

Sources (3)
Operator announced signed 200 MW grid agreement.

Aug 4, 2025 · Recorded actual event

Completed · Announced

Sources (1)
110 kV substation topping-out ceremony.

Oct 13, 2026 · Recorded actual event

JSM is general contractor for the 110 kV substation and approximately 6 km cable route to Wustermark, not verified campus-wide building contractor. JSM reported the substation structural topping-out on October 13, 2026. In its October 19 release, JSM said building-services installation was scheduled for the end of October, with transformer installation to follow. The release names Lupp as construction partner. The 200 MVA substation rating is not 200 MW commissioned IT or proof of energization.

Completed · Announced

Sources (2)
Operator detailed-page Q3 2028 service target; conflicting portfolio wording remains

Q3 2028 · Forecast / planned record

The detailed operator BER02 page gives a Q3 2028 ready-for-service target, while its portfolio page simultaneously retains Q1 2028 text and a Q3 2028 card. These are inconsistent published targets; no confirmed service date, documented delay or supersession sequence is established.

Forecast · Announced

Sources (2)

Participants

maincubes

Developer · Operator

Sources by role
Developer / Operator (1)

Capital & incentives

Capital claims

Reviewed ber financing context

Reported rounded

DTCP's January 13, 2026 platform financing announcement explicitly includes mainHub Berlin development among supported projects. The package comprises €1.775 billion committed facilities plus a €700 million uncommitted accordion across portfolio refinancing and development. No amount is allocated to Nauen in that disclosure.

Source

Site & development

Site location

Reported rounded

Berliner Straße, 14641 Nauen; 52.5935000,12.8929999; approximately 137000 sqm. BER02 is the first building of one up to six building campus.

Source

Land and site control context

Reported rounded

Operator plot area and coordinates confirmed.

Source

Reviewed ber land control context

Reported rounded

Maincubes announced completion of a 14-hectare land purchase in Nauen on 21 October 2024. The city identifies AM:PM Grund Alpha GmbH as the development proponent and maincubes as future operator/implementer. This supports an operator reported acquisition, not a verified current land register owner or purchase price.

Source

Technical specifications

Process water design context

Forecast

Operator describes zero process water usage as a campus design feature; total water use, water sourcing, domestic/fire/construction consumption and measured WUE are not established.

Source

Cooling and power redundancy design

Forecast

Operator specifies n+1 for flexible cooling and power supply topologies, with block, distributed redundant, catcher or N+2C configurations; not all options simultaneously installed or commissioned.

Source

Reviewed ber water design conflict context

Reported rounded

The December 2024 planning rationale envisaged supplementary water cooling above approximately 28°C, with final quantities left to building approval. The current operator page instead advertises zero process water usage as a design feature. The relationship between these descriptions is unverified; neither proves installed equipment or zero total site water consumption. The planning rationale’s account of absent potable water and sewer connections is historical, not a current field observation.

Source

Reviewed ber power participants and milestone context

Reported rounded

JSM is general contractor for the 110 kV substation and approximately 6 km cable route to Wustermark, not verified campus wide building contractor. JSM reported the substation structural topping out on October 13, 2026. In its October 19 release, JSM said building services installation was scheduled for the end of October, with transformer installation to follow. The release names Lupp as construction partner. The 200 MVA substation rating is not 200 MW commissioned IT or proof of energization.

Source

Additional project facts

Heat reuse design context

Forecast

Campus design includes heat recovery for on campus use and intended local district heating; no executed heat offtake agreement or operating delivery is established.

Source

Autonomous operation design upper bound

Forecast

Operator advertises up to 48 hours of autonomous operation and priority fuel delivery. This is a design specification, not tested runtime at every load or proof of installed generation.

Source

Reviewed ber planning approvals context

Reported rounded

Nauen adopted the 6 December 2024 version of Bebauungsplan Rechenzentrum on 25 February 2025. The 2 July 2025 official gazette announced its entry into force. The associated FNP amendment Südliche Erweiterung GE Ost was approved on 6 June 2025 under reference 63.3-01144-25 and became effective with publication. These are zoning instruments, not blanket building or operational approvals.

Source

Reviewed ber parcel scope context

Reported rounded

The December 2024 rationale defines a 14.6 ha planning area in Gemarkung Nauen, Flur 17: 35, 36, 157, 159, 209, 210, 211, 212 and parts of 46/7, 232 and 233. Proposed replacements 35 → 257/258, 36 → 259/260 and 210 → 255/256 were still awaiting administrative adoption. Road parcels include public ownership; other land is described as privately owned. This is a dated planning boundary, not the purchased parcel schedule.

Source

Reviewed ber utility context

Reported rounded

The operator reported a signed 200 MW grid connection agreement with E.DIS in August 2025 and identified E.DIS distribution network supply in March 2026. Contracted connection capacity is separate from 200 MVA equipment and 144–186 MW planned IT. The operator's 2027 supply statement is a dated expectation, not proof of energization.

Source

Reviewed ber service target conflict context

Reported rounded

The detailed operator BER02 page gives a Q3 2028 ready for service target, while its portfolio page simultaneously retains Q1 2028 text and a Q3 2028 card. These are inconsistent published targets; no confirmed service date, documented delay or supersession sequence is established.

Source

Infrastructure & permits

Technical details (5)
Utility service

Reported context

Dedicated substation described as 200 MVA with 110/20 kV transformers; retain MVA separately from grid-contract MW. JSM delivering six-kilometre connection to Wustermark.

Cooling system

Reported context

Air, liquid or hybrid design; PUE <=1.2 target. The December 2024 planning rationale envisaged supplementary water cooling above approximately 28°C, with final quantities left to building approval. The current operator page instead advertises zero process-water usage as a design feature. The relationship between these descriptions is unverified; neither proves installed equipment or zero total site-water consumption. The planning rationale’s account of absent potable-water and sewer connections is historical, not a current field observation.

Fiber

Reported context

Four carrier entry points specified.

Electric grid

Planned or represented

200 MW

The operator reported a signed 200 MW grid-connection agreement with E.DIS in August 2025 and identified E.DIS distribution-network supply in March 2026. Contracted connection capacity is separate from 200 MVA equipment and 144–186 MW planned IT. The operator's 2027 supply statement is a dated expectation, not proof of energization.

Utility service

Planned or represented

200 MVA

Dedicated 200 MVA substation specification; separate from 200 MW grid contract.

Other · Documented

maincubes mainHub Berlin Campus / BER02

Sources (4)

Public-source research. Plans may change. See Evidence for sources and qualifications.