AdaniConneX Taloja AI Campus
- Planned / design
- 240 MW
- Updated
- Oct 29, 2026
AdaniConneX's Taloja campus is an announced AI data centre development in the Navi Mumbai region. CoreWeave's October 2026 announcement describes three 80 MW buildings, or 240 MW of deployment capacity, with an option for a further 240 MW. The expansion option is not included in the base figure, and the source does not explicitly define the deployment measure as IT load. First-phase availability is targeted for mid-2028, not already achieved. Planned systems include direct liquid cooling in GPU halls and non-evaporative chilled water. The broader Navi Mumbai portfolio is not treated as the same physical campus. Exact land-title details, campus grid allocation, carrier commitments and project-specific funding were not established.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
3 buildings
Three 80 MW buildings form the base 240 MW deployment. Source does not explicitly classify MW as IT; additional 240 MW is optional and excluded. Evidence: SRC-N215-ADANICONNEX-TALOJA-T1
Milestones (2)
Oct 6, 2026 · Recorded actual event
Completed · Announced
Sources (1)
- CoreWeave Taloja announcement · Oct 6, 2026 · Primary
2028 · Forecast / planned record
Forecast · Announced
Sources (1)
- CoreWeave Taloja announcement · Oct 6, 2026 · Primary
Participants
Developer · Operator
Sources by role
Developer / Operator (1)
- CoreWeave Taloja announcement · Oct 6, 2026 · Primary
Site & development
Site location
Reported roundedNamed Taloja campus; CoreWeave’s three buildings are a tenant deployment within it, not a separate campus. Exact plot remains undisclosed in reviewed source.
SourceLand and site control context
Reported roundedTaloja locality source confirmed; land area/title unknown.
SourceInfrastructure & permits
Technical details (1)
Reported context
Direct liquid cooling in GPU halls and non-evaporative chilled-water design.