AdaniConneX Taloja AI Campus

Taloja, Maharashtra, IndiaProposed
Evidence
Planned / design
240 MW
Updated
Oct 29, 2026

AdaniConneX's Taloja campus is an announced AI data centre development in the Navi Mumbai region. CoreWeave's October 2026 announcement describes three 80 MW buildings, or 240 MW of deployment capacity, with an option for a further 240 MW. The expansion option is not included in the base figure, and the source does not explicitly define the deployment measure as IT load. First-phase availability is targeted for mid-2028, not already achieved. Planned systems include direct liquid cooling in GPU halls and non-evaporative chilled water. The broader Navi Mumbai portfolio is not treated as the same physical campus. Exact land-title details, campus grid allocation, carrier commitments and project-specific funding were not established.

Capacity

Planned campus capacity MW

Planned / design or future potential

240 MW

Source

Optional expansion capacity MW

Planned / design or future potential

240 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Base three-building deploymentPlanned

3 buildings

Three 80 MW buildings form the base 240 MW deployment. Source does not explicitly classify MW as IT; additional 240 MW is optional and excluded. Evidence: SRC-N215-ADANICONNEX-TALOJA-T1

Milestones (2)
CoreWeave announced Indian entry and Taloja deployment.

Oct 6, 2026 · Recorded actual event

Completed · Announced

Sources (1)
First tenant phase availability target.

2028 · Forecast / planned record

Forecast · Announced

Sources (1)

Participants

AdaniConneX

Developer · Operator

Sources by role
Developer / Operator (1)

Site & development

Site location

Reported rounded

Named Taloja campus; CoreWeave’s three buildings are a tenant deployment within it, not a separate campus. Exact plot remains undisclosed in reviewed source.

Source

Land and site control context

Reported rounded

Taloja locality source confirmed; land area/title unknown.

Source

Infrastructure & permits

Technical details (1)
Cooling system

Reported context

Direct liquid cooling in GPU halls and non-evaporative chilled-water design.