Cartis diligence evidence schedule
GreenScale Tonstad Campus
PRJ-1286 · Site · Tonstad, Norway
Record last updated Oct 29, 2026
Scope and capacity
GreenScale’s Tonstad campus is in site preparation beside Ertsmyra in Sirdal, Norway. The operator describes a 300 MW peak-demand reservation, not IT capacity, and targets first service in 2028. Its December 2025 electrical concession requires an approved detailed plan before electrical construction and grid works before connection; it is not campus-wide building approval or evidence of energization. Sirdal’s August 2026 memorandum reported unresolved zoning appeals, with no later determination verified in this review. Current title, first-phase IT capacity and the full building-permit position remain unverified.
Headline: 300 MW Utility capacity
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (6)
Secured grid power capacity MW · 300 MW
Forecast · GreenScale Tonstad Campus (Project)
Claim 160768 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Tonstad campus specifications
GreenScale · Document date: Not stated · Primary
Source reference: SRC-8105 · Company announcement · Recorded authority: Party primary
Source URL
https://greenscaledc.com/data-centres/tonstad-campus/
https://greenscaledc.com/data-centres/tonstad-campus/
Site location · One four building campus beside Ertsmyra switchyard; 420,000 m² acquired. Operator gives 4440 Tonstad and 58°40′29.3″N 6°44′55.5″E. Do not create four separate projects.
Reported rounded · GreenScale Tonstad Campus (Project)
Claim 160769 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Tonstad campus specifications
GreenScale · Document date: Not stated · Primary
Source reference: SRC-8105 · Company announcement · Recorded authority: Party primary
Source URL
https://greenscaledc.com/data-centres/tonstad-campus/
https://greenscaledc.com/data-centres/tonstad-campus/
Land and site control context · Operator says land acquired; parcel title was not inspected.
Reported rounded · GreenScale Tonstad Campus (Project)
Claim 160770 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Tonstad campus specifications
GreenScale · Document date: Not stated · Primary
Source reference: SRC-8105 · Company announcement · Recorded authority: Party primary
Source URL
https://greenscaledc.com/data-centres/tonstad-campus/
https://greenscaledc.com/data-centres/tonstad-campus/
Electrical concession conditions · The electrical concession requires completion and commissioning by 30 June 2028. The concession holder may apply to extend that deadline. An NVE-approved detailed plan is required before electrical construction. Connection to Ertsmyra depends on necessary works by Glitre Nett and Statnett. The concession does not establish campus wide building approval or actual energization.
Actual · GreenScale Tonstad Campus (Project)
Claim 162492 · Recorded claim type: Actual · Review: Approved · Claim date: Dec 10, 2025
- Tonstad Datapark AS – electrical concession, 10 December 2025
Norwegian Water Resources and Energy Directorate (NVE) · Document date: Dec 10, 2025 · Primary
Source reference: SRC-8230 · Regulatory record · Recorded authority: Official primary
Source URL
https://webfileservice.nve.no/API/PublishedFiles/Download/b3e6c058-9632-4c45-ab55-7d21c2b07d0b/202519658/3448621
https://webfileservice.nve.no/API/PublishedFiles/Download/b3e6c058-9632-4c45-ab55-7d21c2b07d0b/202519658/3448621
Dated planning appeal status · A Sirdal municipal memorandum dated 18 August 2026 records unresolved appeals concerning the 31 October 2024 amendment to the Ertsmyran zoning plan. The council maintained its decision on 9 July 2026 and referred the appeals to the County Governor on 10 July. This is the status reported in that memorandum; no later determination was verified here.
Actual · GreenScale Tonstad Campus (Project)
Claim 162493 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 18, 2026
- Information concerning the data centre – Sirdal municipal memorandum, 18 August 2026
Sirdal municipality · Document date: Aug 18, 2026 · Primary
Source reference: SRC-8231 · Government record · Recorded authority: Official primary
Source URL
https://sirdal.info/informasjon-omkring-datasenteret/
https://sirdal.info/informasjon-omkring-datasenteret/
Reviewed tonstad peak demand scope · GreenScale’s undated FAQ defines its reported 300 MW reservation as absolute peak demand, with lower usage expected in normal operation. This operator definition is not IT capacity or a measurement of delivered power.
Reported rounded · GreenScale Tonstad Campus (Project)
Claim 162652 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Tonstad peak-demand reservation — GreenScale sustainability FAQ
GreenScale · Document date: Not stated · Primary
Source reference: SRC-8330 · Fact sheet · Recorded authority: Party primary
Source URL
https://greenscaledc.com/sustainability/
https://greenscaledc.com/sustainability/
Counterparties and capital
GreenScale · Developer, Operator · CMP-1721
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.