MERLIN Edged Lisbon VFX Campus
- Planned critical IT
- 180 MW
- Updated
- Oct 29, 2026
MERLIN is developing a five-building data centre campus at its VFX site in Vila Franca de Xira, near Lisbon. The plan comprises an initial 80 MW of IT capacity plus 100 MW in three later buildings, for a 180 MW full-campus target. Construction and site preparation are not evidence that the full capacity is operating. The July 2026 update described progress on the initial works and preparation for later buildings, with the latter now targeted to become ready together in the first half of 2029 rather than on the earlier staggered schedule. Power allocations in the investor plan remain distinct from installed IT load. Site-specific financing, measured cooling performance and a complete current permit register were not independently established.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
2 buildings
80 MW IT initial stage within 180 MW plan. Evidence: SRC-N215-MERLIN-NAVALMORAL-M1
3 buildings
100 MW IT later stage; July 2026 simultaneous H1 2029 RFS target supersedes prior staggered plan. Evidence: SRC-N215-MERLIN-NAVALMORAL-M1; SRC-N215-MERLIN-BILBAO-M2
Milestones (3)
Mar 10, 2026 · Recorded actual event
Completed · Announced
Sources (1)
- MERLIN Capital Markets Day, Navalmoral slides 37–39 · Mar 10, 2026 · Primary
Jul 28, 2026 · Recorded actual event
Completed · Announced
Sources (1)
- MERLIN half-year development update · Jul 28, 2026 · Primary
2029 · Forecast / planned record
Forecast · Announced
Sources (1)
- MERLIN half-year development update · Jul 28, 2026 · Primary
Participants
Developer
Sources by role
Developer (1)
- MERLIN Capital Markets Day, Navalmoral slides 37–39 · Mar 10, 2026 · Primary
Capital & incentives
Capital claims
Reviewed lis partners investment context
Source reportA mayoral interview posted by the municipality on October 8, 2024 describes Lisbon Campus as a joint MERLIN Properties and Edged Energy project combining a data centre and technology innovation centre, with approximately €1 billion of investment. This is combined project context, not proven equity ownership, title, allocated data centre budget or financing.
SourceSite & development
Technical specifications
Reviewed lis cooling context
Source reportEdged advertises N+1 glycol heat transfer with rooftop air cooled chillers and secondary closed loop evaporators, with cooling WUE of 0.00 L/kWh. These are design specifications, not measured performance or zero total site water consumption.
SourceReviewed lis connectivity power context
Source reportEdged’s site specification advertises two meet me rooms, three diverse fibre entry points, dedicated substations, N+1 UPS and generators, and redundant A+B distribution. Named contracted carriers, installed equipment and energization are not verified by these specifications.
SourceAdditional project facts
Reviewed lis permit context
Source reportMERLIN’s 2024 annual report states that LIS01-VFX had a licence and power, with earthworks already begun by year end. This is issuer reported LIS01 status, not an independently inspected municipal instrument or approval of all five buildings. The report does not establish energized supply or commissioned IT capacity.
SourceInfrastructure & permits
Technical details (1)
Reported context
March investor plan describes granted power for buildings 03–05.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.