Princeton Digital Group TY1 Saitama Campus
- Planned critical IT
- 96 MW
- Updated
- Oct 29, 2026
PDG’s TY1 campus in Saitama retains a 96 MW IT design; its April 2025 launch covered only the 48 MW first phase. OCP-hosted operator assessments describe 48 MW per building and 66 kV supply design, not measured load or verified utility contracts. DC2’s January 2025 assessment targets June 2028 services but uses an unresolved TY2 internal label; its relationship to the existing schedule remains unclear. Assessment PUE responses are not measured performance. Published investment values are not expenditure or loan facilities. Current phase-two delivery, occupied load, title and permit identifiers remain unverified.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Milestones (2)
Mar 27, 2024 · Recorded actual event
Completed · Announced
Sources (1)
Apr 24, 2025 · Recorded actual event
Completed · Announced
Sources (2)
Participants
Site & development
Land and site control context
Reported rounded33,000 Square metre site; built to suit by Lendlease Data Centre Partners for PDG. Legal freehold/title ownership not independently established.
SourceSite location
Reported roundedSaitama City, Saitama Prefecture, Japan 331-0823. Operator coordinates: 35.935982, 139.607999. The OCP-hosted TY1 DC1 self assessment dated January 31, 2025 identifies 2-1917 Nissincho, Kita ku, Saitama City, Saitama Prefecture, Japan. It lists 48 MW critical IT power, 12,096 m² white space, active/standby 66 kV TEPCO supply and air cooled chillers providing chilled water to data halls. These are operator assessed facility/design specifications, not an inspected utility contract, cadastral title or measured operating load.
SourceAdditional project facts
Reviewed pdg dc2 conflict context
Source reportOCP’s registry separately lists TY1 DC2 and links its approved operator assessment. The assessment, dated January 31, 2025, describes 48 MW critical IT at the same address, with build in progress status and estimated live services June 30, 2028. Its internal location name says PDG TY2, while its title and registry say TY1 DC2. Nomenclature, current delivery status and the relationship to the existing operator schedule remain unresolved; certification does not establish commissioning.
SourceReviewed pdg technical bases context
Source reportThe OCP-hosted operator assessments dated January 31, 2025 use 48 MW critical IT per building and a PUE response category above 1.3 at 80% maximum utilization. The relationship of those assessment responses to existing operator technical specifications remains unresolved. They do not establish measured operating PUE or revise the retained 96 MW campus design headline.
SourceInfrastructure & permits
Technical details (4)
Reported context
66 kV diverse feeds, distributed redundant UPS, seven-minute end-of-life battery autonomy expandable to ten minutes, and 48-hour on-site full-load support in factsheet. Do not infer current utility contract.
Reported context
Factsheet specifies N+1 air-cooled chillers, dual chilled-water vertical loops and over four minutes thermal storage. Launch release also reports liquid-cooling capability and design PUE below 1.34.
Reported context
Carrier-neutral, three diverse entries and four meet-me rooms per factsheet; connectivity toward central/eastern Tokyo, Inzai and cable landings.
Planned or represented
Distributed redundant UPS, seven-minute end-of-life battery autonomy expandable to ten minutes; factsheet resilience design rather than an operating-load measurement.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.