Digital Connexion Chennai Campus / MAA10
- Planned / design
- 100 MW
- Updated
- Oct 29, 2026
Digital Connexion’s Ambattur campus in Chennai is planned for four buildings and approximately 100 MW of potential IT capacity. MAA10 launched in January 2024 with an operator specification of 20 MW IT. Ind-Ra’s September 2026 rationale reports 6 MW ready for service and 16.6 MW of remaining MEP works targeting March 2027, but gives a 22.4 MW Building 1 total. Those components sum to 22.6 MW; neither that discrepancy nor the difference from the operator specification is reconciled. Reported offtake agreements cover 21 MW, not occupied load.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Opened January 2024; 20 MW IT specification, not measured load. Evidence: SRC-N220-DIGITAL-CONNEXION-MAA10-D2; SRC-N220-DIGITAL-CONNEXION-MAA10-D4
3 buildings
Four-building 100 MW campus potential; remaining buildings not asserted operating. Evidence: SRC-N220-DIGITAL-CONNEXION-MAA10-D1; SRC-N220-DIGITAL-CONNEXION-MAA10-D5
Milestones (2)
Jan 11, 2024 · Recorded actual event
Completed · Announced
Sources (1)
- Operator launch account · Primary
May 22, 2024 · Recorded actual event
Completed · Announced
Sources (1)
- Digital Connexion/DE-CIX release · May 22, 2024 · Primary
Participants
Developer · Operator
Sources by role
Developer / Operator (1)
- 20 MW IT and 100 MW expansion scope · Primary
Capital & incentives
Capital claims
Reviewed maa10 capital context
Reported roundedInd-Ra’s September 16, 2026 rationale reports an estimated INR 14.2 billion Building 1 project cost and availability of an INR 9.25 billion construction finance term facility. It says all committed equity had been infused by end-August 2026. These are distinct cost, facility and equity statements; the facility amount is not verified drawn or outstanding debt, and the equity statement gives no total amount. The September 2026 rationale anticipates conversion of construction finance to receivables discounting finance upon commissioning; it does not confirm refinancing closure or final terms.
SourceReviewed maa10 lenders context
Reported roundedThe issuer reported bank table, as of September 16, 2026, lists Axis Bank Limited: Term Loan, rated amount INR 2,300 million, issuance April 22, 2024; and ICICI Bank: Term Loan, rated amount INR 6,950 million, issuance April 19, 2024. Both rows show maturity December 31, 2027 and IND AA-/Stable. These are rated amounts, not verified disbursements or current outstanding balances; issuance dates are source table fields, not independently confirmed financial close dates.
SourceReviewed maa10 revenue context
Reported roundedInd-Ra’s September 2026 rationale reports rental receipts had begun for 0.8 MW and forecasts rental commencement for another 5.2 MW on October 15, 2026 and 15 MW on June 30, 2027. These are rental milestones, not measured electrical load or independently verified commissioning; an elapsed forecast date does not prove execution.
SourceSite & development
Additional project facts
Reviewed maa10 entity context
Reported roundedInd-Ra identifies DXDC Chennai Private Limited, formerly BAM DLR Chennai Private Limited, as the entity developing MAA10, the first phase of a Chennai campus with approximately 100 MW potential IT capacity. This is project entity evidence, not parcel title.
SourceReviewed maa10 commercial context
Reported roundedInd-Ra’s September 2026 rationale reports offtake agreements covering 21 MW, including approximately 20.2 MW under a ten year enterprise customer agreement. Contracted capacity is not occupied electrical load; the customer is unnamed.
SourceReviewed maa10 currentness context
Reported roundedInd-Ra’s September 2026 rationale reports 6 MW ready for service, with MEP works for the stated remaining 16.6 MW targeting March 2027. It repeatedly gives approximately 22.4 MW as the planned Building 1 total, increased from 20.4 MW. The components sum to 22.6 MW, not 22.4 MW; the discrepancy remains unresolved. The operator page still lists a 20 MW specification. These figures do not establish occupied load or a reconciled replacement capacity.
SourceInfrastructure & permits
Technical details (3)
Reported context
MAA10 specifies 20 MW and UPS 5/4 distribution; do not label all 100 MW live.
Reported context
N+2 cooling specified for MAA10; do not assign capacity to all future buildings.
Reported context
DE-CIX point of presence confirmed by joint announcement.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (4)
Proposed · Chennai, Tamil Nadu, India
Same locality: Chennai
Compare in a collectionUnder construction · Chennai, Tamil Nadu, India
Same locality: Chennai
Compare in a collectionPreconstruction · Chennai, Tamil Nadu, India
Same locality: Chennai
Compare in a collectionPartially operational · Chennai, Tamil Nadu, India
Same locality: Chennai
Compare in a collection