EverWind Point Tupper Data Centre Campus

PRJ-1305 · Site · Point Tupper, Nova Scotia, Canada

Record last updated Oct 29, 2026

Scope and capacity

EverWind proposes a 420 MW campus at Point Tupper, Nova Scotia, comprising 95 MW initially and a later 325 MW expansion; the electrical basis is not explicitly IT load. The developer targets late 2027 and 2028, subject to conditions, and says initial grid studies are complete, not that service is energized. Planned campus investment exceeds CAD8 billion, separate from CAD2 billion for wind. Its FAQ names Anthropic in joint ratepayer commitments. On 20 October 2026, Membertou said it had not partnered in or invested in the campus. Full expansion approval, campus financing close and specialist operating partners remain unverified.

Headline: 420 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (7)

Planned campus capacity MW · 420 MW

Planned / design or future potential · EverWind Point Tupper Data Centre Campus (Project)

Claim 160843 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. EverWind announces $10 billion investment in Point Tupper data centre campus and renewable energy portfolio across Nova Scotia

    EverWind · Document date: Oct 16, 2026 · Primary

    Source reference: SRC-8162 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwindfuels.com/2026/10/everwind-announces-10-billion-investment-in-point-tupper-data-centre-campus-and-renewable-energy-portfolio-across-nova-scotia/

Site location · EverWind owned, previously developed land inside Point Tupper Heavy Industrial Park. Exact data center parcel boundary and street address have not been disclosed in inspected pages.

Reported rounded · EverWind Point Tupper Data Centre Campus (Project)

Claim 160844 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. The Future has a home | Everwind

    EverWind · Document date: Not stated · Primary

    Source reference: SRC-8163 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwinddc.com/

Land and site control context · Operator identifies its owned brownfield industrial land, but no title record or exact data center footprint independently recovered.

Reported rounded · EverWind Point Tupper Data Centre Campus (Project)

Claim 160845 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. The Future has a home | Everwind

    EverWind · Document date: Not stated · Primary

    Source reference: SRC-8163 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwinddc.com/

Initial phase capacity MW · 95 MW

Planned / design or future potential · EverWind Point Tupper Data Centre Campus (Project)

Claim 160846 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. EverWind announces $10 billion investment in Point Tupper data centre campus and renewable energy portfolio across Nova Scotia

    EverWind · Document date: Oct 16, 2026 · Primary

    Source reference: SRC-8162 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwindfuels.com/2026/10/everwind-announces-10-billion-investment-in-point-tupper-data-centre-campus-and-renewable-energy-portfolio-across-nova-scotia/

Later phase capacity MW · 325 MW

Planned / design or future potential · EverWind Point Tupper Data Centre Campus (Project)

Claim 160847 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. EverWind announces $10 billion investment in Point Tupper data centre campus and renewable energy portfolio across Nova Scotia

    EverWind · Document date: Oct 16, 2026 · Primary

    Source reference: SRC-8162 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwindfuels.com/2026/10/everwind-announces-10-billion-investment-in-point-tupper-data-centre-campus-and-renewable-energy-portfolio-across-nova-scotia/

Reviewed dated indigenous participation clarification · On 20 October 2026, Membertou stated that it was not partnered in, and had not invested in, the data centre project at that time. Its wind project partnership is separate. EverWind’s 16 October announcement and current FAQ describe campus stake negotiations, not a completed investment.

Actual · EverWind Point Tupper Data Centre Campus (Project)

Claim 162658 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Membertou Community Update on Partnership with Everwind Fuels

    Membertou · Document date: Oct 20, 2026 · Primary

    Source reference: SRC-8336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://membertou.ca/membertou-community-update-on-partnership-with-everwind-fuels/

  2. EverWind announces $10 billion investment in Point Tupper data centre campus and renewable energy portfolio across Nova Scotia

    EverWind · Document date: Oct 16, 2026 · Corroborating

    Source reference: SRC-8162 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwindfuels.com/2026/10/everwind-announces-10-billion-investment-in-point-tupper-data-centre-campus-and-renewable-energy-portfolio-across-nova-scotia/

  3. The Future has a home | Everwind

    EverWind · Document date: Not stated · Corroborating

    Source reference: SRC-8163 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwinddc.com/

Reviewed named AI relationship context · EverWind’s FAQ names Anthropic in joint ratepayer commitments, and Membertou’s 20 October statement describes the announced Anthropic relationship. This supports attributed relationship context, not verified lease duration, ownership or a specialist operating role.

Actual · EverWind Point Tupper Data Centre Campus (Project)

Claim 162659 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Membertou Community Update on Partnership with Everwind Fuels

    Membertou · Document date: Oct 20, 2026 · Corroborating

    Source reference: SRC-8336 · Company announcement · Recorded authority: Party primary

    Source URL

    https://membertou.ca/membertou-community-update-on-partnership-with-everwind-fuels/

  2. The Future has a home | Everwind

    EverWind · Document date: Not stated · Primary

    Source reference: SRC-8163 · Company announcement · Recorded authority: Party primary

    Source URL

    https://everwinddc.com/

Counterparties and capital

EverWind · Developer · CMP-1725

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.