Keppel Morwell AI Data Centre Campus

Hazelwood North, Victoria, AustraliaProposed
Evidence
Utility capacity
720 MW
Updated
Oct 29, 2026

Keppel proposes a 123-hectare AI data centre campus at Firimins Lane and Tramway Road, Hazelwood North, near Morwell. Its up-to-720 MW powerbank is prospective gross power, not IT load or energized supply. Keppel has an Agreement for Lease with Lightwood Group, with early-access fees before planned long-term fund leases. Latrobe City Council’s September 2026 update said no planning application had been lodged and consultation was planned for late 2026. Power and water contracts remain predevelopment work. Phase dates, tenant commitments and campus-specific financing remain unverified.

Capacity

Gross power capacity MW

Forecast

720 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (2)
Lease and early site access agreement announced; exact date established by SGX issuer filing SG260115OTHRZVEB

Jan 15, 2026 · Recorded actual event

Completed · Announced

Sources (2)
Council update reported no planning application lodged

Sep 2026 · Recorded actual event

Completed · Announced

Sources (1)

Participants

Keppel Ltd.

Developer · Operator

Sources by role
Developer / Operator (1)

Site & development

Site location

Reported rounded

Firimins Lane and Tramway Road, Hazelwood North, Victoria, Australia. Council identifies the 123-hectare proposal. Preserve council spelling rather than invent a street number.

Source

Land and site control context

Reported rounded

Lightwood Group is landowner. Keppel holds rights to lease 123 hectares, with annual early access fee before proposed long term fund leases.

Source

Infrastructure & permits

Technical details (4)
Electric grid

Reported context

Potential dedicated connection to nearby terminal stations; power contracts remain predevelopment work. Do not imply energized or contracted 720 MW.

Cooling system

Reported context

Existing water infrastructure and proposed non-potable cooling supply; detailed cooling system and water allocation not disclosed.

Fiber

Reported context

Near intercity dark-fibre networks serving Melbourne, Sydney and Canberra; no signed carrier agreement evidenced.

Water supply

Planned or represented

Non-potable cooling supply proposed; water allocation and executed supply contracts remain unestablished.

Other · Documented

Keppel Morwell AI Data Centre Campus

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.