Bridge Data Centres MY07
- Planned critical IT
- 374 MW
- Updated
- Oct 29, 2026
Bridge Data Centres’ MY07 campus in Ulu Tiram, Johor, is specified for 374 MW of IT capacity across eight buildings on approximately 65 acres. This is full-campus design capacity, not operating load. Changlan reports that its 275 kV cable accessories for the MY07 B1 mechanical/electrical project entered service and connected to TNB’s grid in June 2025, an equipment milestone rather than campus-wide energization. Bridge’s September 2026 account describes active operations and reclaimed water supplying cooling without potable-water reliance. Operating IT capacity, exact parcel title and campus-specific financing remain unverified. MY07 is separate from MY06 at Sedenak.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Milestones (3)
Sep 2, 2025 · Recorded actual event
Completed · Announced
Sources (1)
May 22, 2026 · Recorded actual event
Completed · Announced
Sources (1)
- Advancing AI Infrastructure with Liquid Cooling in Malaysia · May 22, 2026 · Primary
Sep 2, 2026 · Recorded actual event
Completed · Announced
Sources (1)
- Building Malaysia’s Digital Future · Sep 2, 2026 · Primary
Participants
Site & development
Site location
Reported roundedUlu Tiram, Johor, Malaysia, approximately 65 acres. Prefer the operator’s locality over conflicting secondary Pasir Gudang labels.
SourceLand and site control context
Reported roundedOperator specifies 65 acres. Secondary parcel and Paragon transaction leads were not primary verified; no parcel/title/price is accepted.
SourceAdditional project facts
Reviewed b1 cable equipment milestone
ActualIn its 2025 ESG report, Changlan says the 275 kV cable accessories it supplied for the BDC MY07 B1 mechanical/electrical project entered service and connected to TNB’s main grid in June 2025. This is a supplier reported equipment milestone, not proof of B1 opening, whole campus energization or any operating IT capacity.
SourceInfrastructure & permits
Technical details (3)
Reported context
275 kV intake is published. A 400 MW TNB agreement appears in secondary leads but was not primary-verified and is not accepted here.
Reported context
Johor Special Water partnership uses IWK treated effluent, membrane bioreactor and reverse osmosis. By September 2026, operator claims reclaimed water supplies all cooling needs without potable-water reliance. Vertiv is named in a site-specific liquid-cooling test report.
Reported context
Operator September 2026 report states reclaimed water supplies cooling needs without potable-water reliance, through Johor Special Water and IWK treated effluent. Not a claim of zero total site water use.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.