Cartis diligence evidence schedule

Keppel Morwell AI Data Centre Campus

PRJ-1281 · Site · Hazelwood North, Victoria, Australia

Record last updated Oct 29, 2026

Scope and capacity

Keppel proposes a 123-hectare AI data centre campus at Firimins Lane and Tramway Road, Hazelwood North, near Morwell. Its up-to-720 MW powerbank is prospective gross power, not IT load or energized supply. Keppel has an Agreement for Lease with Lightwood Group, with early-access fees before planned long-term fund leases. Latrobe City Council’s September 2026 update said no planning application had been lodged and consultation was planned for late 2026. Power and water contracts remain predevelopment work. Phase dates, tenant commitments and campus-specific financing remain unverified.

Headline: 720 MW Utility capacity

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Gross power capacity MW · 720 MW

Forecast · Keppel Morwell AI Data Centre Campus (Project)

Claim 160752 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Keppel secures 720MW powerbank for AI data centre campus near Melbourne, expanding powerbank to over 1GW

    Keppel Ltd. · Document date: Not stated · Primary

    Source reference: SRC-8086 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.keppel.com/media/keppel-secures-720mw-powerbank-for-ai-data-centre-campus-near-melbourne-expanding-powerbank-to-over-1gw/

Site location · Firimins Lane and Tramway Road, Hazelwood North, Victoria, Australia. Council identifies the 123-hectare proposal. Preserve council spelling rather than invent a street number.

Reported rounded · Keppel Morwell AI Data Centre Campus (Project)

Claim 160753 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Proposed Developments in Our Region

    Latrobe City Council · Document date: Not stated · Primary

    Source reference: SRC-8087 · Government record · Recorded authority: Official primary

    Source URL

    https://www.latrobe.vic.gov.au/Property/Development/Proposed_Developments_in_Our_Region

Land and site control context · Lightwood Group is landowner. Keppel holds rights to lease 123 hectares, with annual early access fee before proposed long term fund leases.

Reported rounded · Keppel Morwell AI Data Centre Campus (Project)

Claim 160754 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Keppel secures 720MW powerbank for AI data centre campus near Melbourne, expanding powerbank to over 1GW

    Keppel Ltd. · Document date: Not stated · Primary

    Source reference: SRC-8086 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.keppel.com/media/keppel-secures-720mw-powerbank-for-ai-data-centre-campus-near-melbourne-expanding-powerbank-to-over-1gw/

Counterparties and capital

Keppel Ltd. · Developer, Operator · CMP-0209

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.