Skip to content

Compute Nordic Mikkeli AI Campus

Mikkeli, FinlandUnder construction
Evidence
Planned critical IT
165 MW
Updated
Oct 29, 2026

Compute Nordic Finland is developing an AI data centre campus at Visulahti in Mikkeli. In September 2026, Cerebras announced seven-year service orders associated with phased capacity growing from 50 MW to 80 MW and ultimately 165 MW of IT capacity. These are successive stages, not amounts to add together, and construction of the initial 50 MW phase does not establish a currently operating 165 MW facility. The planned design includes closed-loop cooling and heat recovery. A municipal study identifies the project and discusses regional investment potential, but that estimate is not a financing close. Binding grid terms, specific carrier routes, parcel-title documentation and permit identifiers were not verified in the reviewed sources.

Capacity

Target IT capacity MW

Planned / design or future potential

165 MW

Source

Staged IT capacity 50 MW

Forecast

50 MW

Source

Staged IT capacity 80 MW

Forecast

80 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Initial 50 MW IT stageUnder construction

Initial stage under construction as of September 2026; 50 then 80 then 165 MW are successive totals, not additive phases. Evidence: SRC-N215-COMPUTE-MIKKELI-C1

Milestones (2)
City identified Compute Nordic’s Visulahti project in economic-impact study.

Feb 6, 2026 · Recorded actual event

Completed · Announced

Sources (1)
Cerebras announced seven-year service orders and initial construction.

Sep 1, 2026 · Recorded actual event

Completed · Announced

Sources (1)

Participants

Cerebras Systems

Customer

Sources by role
Customer (1)
Compute Nordic Finland

Developer · Operator

Sources by role
Developer / Operator (1)

Capital & incentives

Capital claims

Reviewed mik contract scope context

Source report

NYAB Finland announced a project management contract with Compute Nordic Finland on February 18, 2026. Construction depended on separate orders; eventual contract scope could reach approximately €100 million. Its historical scope included two 100 MW data halls plus supporting works, without defining the MW basis. This is neither committed campus financing nor a replacement for the later 165 MW IT plan.

Source

Site & development

Site location

Reported rounded

Compute Nordic Finland’s Visulahti project; distinct operator identity from nearby FCDC development. Exact parcel reference not established.

Source

Land and site control context

Reported rounded

City source confirms Visulahti locality; lease title not inspected.

Source

Additional project facts

Reviewed mik heat context

Source report

ESE-Energia’s September 16, 2026 announcement reports a signed letter of intent with Compute Nordic Finland to assess district heating reuse. Technical, commercial and investment feasibility remained to be studied; it does not establish a heat delivery contract or completed investment.

Source

Reviewed mik lease context

Source report

The May 24, 2024 development agency announcement reports an official city decision for a roughly ten hectare Visulahti lease. Although it also describes an agreement as entered into, it says the parties would sign after the appeal period. Subsequent execution and current registered lease title are therefore not established by this announcement.

Source

Reviewed mik authority permit context

Source report

Mikkeli’s February 17, 2026 committee minutes describe Compute Nordic Finland’s Visulahti project as having received a construction permit, with a historical maximum of 200 MW, separately from FCDC. The MW basis and original permit conditions are not specified. This authority reported scope does not replace September’s 165 MW IT contract plan.

Source

Infrastructure & permits

Technical details (1)
Cooling system

Reported context

Closed-loop cooling and heat-recovery design.

Public-source research. Plans may change. See Evidence for sources and qualifications.