CloudHQ CDG Lisses Campus

Lisses, FrancePartially operational
Evidence
Planned critical IT
150 MW
Updated
Oct 29, 2026

CloudHQ’s CDG campus in Lisses markets approximately 150 MW of critical IT design, comprising two 74.4 MW buildings. A June 2025 facility inauguration does not establish full-campus commissioning. Infrastructure includes an on-site 225 kV substation, diverse fiber ducts, cooling and district-heat reuse design. A November 2022 joint release reported acquisition of approximately 137,000 m² and a heat-network investment commitment; current title and delivered heat remain unverified. Géorisques lists an authorized operating installation, with 2025 supplementary prescriptions and an inspection whose conditions and findings have not been reviewed.

Capacity

Design IT capacity MW

Design

150 MW

Source

Detailed building sum IT capacity MW

Design

148.8 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (3)
Environmental authorization referenced in prefectural record.

Feb 2, 2022 · Recorded actual event

Completed · Announced

Sources (1)
Foundation-stone ceremony reported by contractor.

Nov 22, 2022 · Recorded actual event

Completed · Announced

Sources (1)
Facility inauguration recorded in contractor annual report.

Jun 2025 · Recorded actual event

Completed · Announced

Sources (1)

Participants

CloudHQ

Developer · Operator

Sources by role
Developer / Operator (1)

Capital & incentives

Capital claims

Reviewed cdg investment context

Reported rounded

The November 22, 2022 joint release estimated total project investment above €1 billion excluding tax. This is a historical estimate, not committed financing or final expenditure.

Source

Reviewed cdg heat context

Reported rounded

The November 22, 2022 release reported CloudHQ’s commitment to invest several million euros in interconnecting its Lisses site with the future Corbeil-Essonnes heat network, under a protocol approved by Grand Paris Sud’s community bureau on February 15, 2022. Actual heat delivery or completion of the interconnection was not established.

Source

Site & development

Site location

Reported rounded

ZA Léonard de Vinci, rue Léonard de Vinci, 91090 Lisses; 48.59768,2.40782. Two planned 74.4 MW IT buildings form one CDG campus.

Source

Land and site control context

Reported rounded

Business park address and operator coordinates identify the Lisses site. A joint release dated 22 November 2022 reported CloudHQ had acquired approximately 137,000 m² in the Léonard de Vinci business park from SPLA-IN, the Grand Paris Aménagement / Grand Paris Sud joint company. Current title and the exact closing date remain unverified.

Source

Additional project facts

Reviewed cdg contractor context

Reported rounded

The November 22, 2022 joint release assigned first phase construction, including building works, cooling and electrical distribution, to Eiffage Génie Civil and Eiffage Énergie Systèmes. These are attributed first phase work package roles, not a legal entity merge or proof of campus wide completion.

Source

Reviewed cdg registry context

Reported rounded

Géorisques lists CLOUDHQ FRANCE installation 0006523753 at rue Léonard de Vinci, Lisses, as operating with authorization. It lists supplementary prescriptions dated 31 July 2025 and an inspection on 10 December 2025. The order conditions and inspection findings remain unverified; these entries do not establish blanket compliance or both buildings’ commissioned IT load.

Source

Infrastructure & permits

Technical details (3)
Electric grid

Reported context

Operator reports new on-site 225 kV substation.

Cooling system

Reported context

Contractor confirms cooling-system delivery and district heat-reuse design; exact cooling topology not established.

Fiber

Reported context

Diverse ducts to two interconnection points.

Other · Documented

CloudHQ CDG Lisses Campus

Sources (2)

Public-source research. Plans may change. See Evidence for sources and qualifications.