GreenScale Tonstad Campus
- Utility capacity
- 300 MW
- Updated
- Oct 29, 2026
GreenScale’s Tonstad campus is in site preparation beside Ertsmyra in Sirdal, Norway. The operator describes a 300 MW peak-demand reservation, not IT capacity, and targets first service in 2028. Its December 2025 electrical concession requires an approved detailed plan before electrical construction and grid works before connection; it is not campus-wide building approval or evidence of energization. Sirdal’s August 2026 memorandum reported unresolved zoning appeals, with no later determination verified in this review. Current title, first-phase IT capacity and the full building-permit position remain unverified.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Milestones (2)
Feb 12, 2026 · Recorded actual event
Completed · Announced
Sources (1)
- Site preparation begins · Feb 12, 2026 · Primary
2028 · Forecast / planned record
Forecast · Announced
Sources (1)
- Tonstad campus specifications · Primary
Participants
Developer · Operator
Sources by role
Developer / Operator (1)
- Tonstad campus specifications · Primary
Site & development
Site location
Reported roundedOne four building campus beside Ertsmyra switchyard; 420,000 m² acquired. Operator gives 4440 Tonstad and 58°40′29.3″N 6°44′55.5″E. Do not create four separate projects.
SourceLand and site control context
Reported roundedOperator says land acquired; parcel title was not inspected.
SourceAdditional project facts
Electrical concession conditions
ActualThe electrical concession requires completion and commissioning by 30 June 2028. The concession holder may apply to extend that deadline. An NVE-approved detailed plan is required before electrical construction. Connection to Ertsmyra depends on necessary works by Glitre Nett and Statnett. The concession does not establish campus wide building approval or actual energization.
SourceDated planning appeal status
ActualA Sirdal municipal memorandum dated 18 August 2026 records unresolved appeals concerning the 31 October 2024 amendment to the Ertsmyran zoning plan. The council maintained its decision on 9 July 2026 and referred the appeals to the County Governor on 10 July. This is the status reported in that memorandum; no later determination was verified here.
SourceReviewed tonstad peak demand scope
Reported roundedGreenScale’s undated FAQ defines its reported 300 MW reservation as absolute peak demand, with lower usage expected in normal operation. This operator definition is not IT capacity or a measurement of delivered power.
SourceInfrastructure & permits
Technical details (3)
Reported context
Industrial zoning; adjacent high-voltage connection, substation less than 1 km away.
Reported context
Operator promotes climate-enabled free cooling; PUE 1.2 is a design claim, not measured live performance.
Reported context
Carrier-neutral fiber and diverse routes advertised; named carriers not established.
Project map
Other · Documented
GreenScale Tonstad Campus
Sources (1)
- Tonstad campus specifications · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.