Stream PHXA Goodyear Campus

PRJ-1289 · Site · Goodyear, Arizona, United States

Record last updated Oct 29, 2026

Scope and capacity

Stream's PHXA campus is at 2950 South Litchfield Road in Goodyear, Arizona. The current plan covers 157 acres and seven buildings with 280 MW of full-build critical IT capacity. The first two buildings serve tenants, but the entire target is not presented as operational. The dedicated APS substation's ultimate 480 MW rating is a separate utility figure. Stream announced commissioning of Phoenix I in January 2021, following a Cox Business connectivity announcement in July 2020. Current operator material describes multiple carriers and closed-loop chillers at its new Phoenix facility; this does not establish identical equipment in every future building. Current campus operating MW, legal parcel ownership and project-specific financing remain unverified.

Headline: 280 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Jump to a claim (6)

Target IT capacity MW · 280 MW

Planned / design or future potential · Stream PHXA Goodyear Campus (Project)

Claim 160780 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Phoenix Data Center - Stream Data Centers in Arizona

    Stream Data Centers · Document date: Not stated · Primary

    Source reference: SRC-8113 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.streamdatacenters.com/locations/phoenix/

Site location · 2950 S. Litchfield Road, Goodyear, AZ 85338; 157-acre campus, seven planned buildings. Street address is confirmed; no surveyed parcel polygon recovered.

Reported rounded · Stream PHXA Goodyear Campus (Project)

Claim 160781 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Phoenix Data Center - Stream Data Centers in Arizona

    Stream Data Centers · Document date: Not stated · Primary

    Source reference: SRC-8113 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.streamdatacenters.com/locations/phoenix/

Land and site control context · Operator identifies the campus footprint; legal title holder and current financing vehicle are not independently established.

Reported rounded · Stream PHXA Goodyear Campus (Project)

Claim 160782 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Phoenix Data Center - Stream Data Centers in Arizona

    Stream Data Centers · Document date: Not stated · Primary

    Source reference: SRC-8113 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.streamdatacenters.com/locations/phoenix/

Reviewed phx acquisition context · Stream’s February 15, 2019 announcement reports acquisition of a 418,000-square foot facility on 157 acres in Goodyear for campus development. This is historical issuer reported acquisition, not current registered title or a verified purchase price.

Source report · Stream PHXA Goodyear Campus (Project)

Claim 162661 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Stream Phoenix campus acquisition announcement

    Stream Data Centers via PR Newswire · Document date: Feb 15, 2019 · Primary

    Source reference: SRC-8338 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.prnewswire.com/news-releases/stream-data-centers-to-develop-hyperscale-data-center-campus-in-phoenix-market-300796378.html

Reviewed phx siteplan cooling context · The July 2023 council agenda ordinance reports May 24, 2023 site plan approval for five two storey, approximately 400,000-square foot buildings on the roughly 104-acre expansion area. It describes rooftop air cooled chillers and proposed PAD screening changes. The unsigned agenda copy is not evidence of final rezoning enactment or completed buildings.

Source report · Stream PHXA Goodyear Campus (Project)

Claim 162662 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Goodyear agenda ordinance 2023-1574 — unsigned copy

    City of Goodyear · Document date: Not stated · Primary

    Source reference: SRC-8339 · Government record · Recorded authority: Official primary

    Source URL

    https://public.destinyhosted.com/goodydocs/2023/CC/20230710_1474/1542_2._Ordinance_No._2023-1574.pdf

Reviewed phx infrastructure context · Stream’s case study reports completed relocation of sewer infrastructure to the western boundary and road upgrades on the eastern side. It says its onsite substation supplies the campus and provides a through flow path to neighbouring development. This does not verify that its ultimate 480 MW rating is energized.

Source report · Stream PHXA Goodyear Campus (Project)

Claim 162663 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Developing Phoenix I-VII: How Stream Data Centers and the City of Goodyear Delivered a Win-Win-Win

    Stream Data Centers · Document date: Not stated · Primary

    Source reference: SRC-8117 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.streamdatacenters.com/wp-content/uploads/2026/01/SDC-Goodyear-CaseStudy-251218.pdf

Counterparties and capital

Stream Data Centers · Developer, Operator · CMP-1344

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.