Skip to content

CloudHQ MSP Campus

Chaska, Minnesota, United StatesProposed
Evidence
Planned critical IT
200 MW
Updated
Oct 29, 2026

CloudHQ MSP Campus. 2007 Schoolmaster Drive, West Creek Corporate Center. Operator coordinates 44.81068,-93.63557. Up to 200 MW planned critical IT in one or two buildings; no operational capacity established. Planned, preliminary approval only. City says no final site-plan/plat application submitted and no final review timeline. On-site substation would connect directly to Xcel transmission, not Chaska distribution. System-impact study remains a stated condition. Air-based chillers proposed; anticipated annual water use 14 million gallons, not a measured operating figure. Private concrete-encased ducts to telecommunications providers. Adjacent Stream/UnitedHealth sites are separate campuses. City reports no tax relief applied for or offered; campus financing not disclosed in reviewed sources. Exact current operating load and unverified legal or financial details remain unknown.

Capacity

Target critical IT capacity MW

Planned / design or future potential

200 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (4)
City Council concept approval.

Aug 15, 2022 · Recorded actual event

Completed · Announced

Sources (1)
Final AUAR adopted.

Jan 9, 2023 · Recorded actual event

Completed · Announced

Sources (1)
Council conditional-use approval.

Oct 16, 2023 · Recorded actual event

Completed · Announced

Sources (1)
Council preliminary site-plan/plat approval.

Oct 21, 2024 · Recorded actual event

Completed · Announced

Sources (1)

Participants

CloudHQ

Developer · Operator

Sources by role
Developer / Operator (1)

Site & development

Site location

Reported rounded

2007 Schoolmaster Drive, West Creek Corporate Center. Operator coordinates 44.81068,-93.63557.

Source

Reviewed msp area context

Source report

CloudHQ advertises 1.1 million sq ft; Chaska describes approximately 1.5 million sq ft. Measurement bases and design versions remain unreconciled; neither establishes completed or occupied IT space.

Source

Additional project facts

Reviewed msp auar scope context

Source report

The 2022 Kelzer AUAR order and attached June scoping document identify a 72.3-acre study area comprising parcels 300311090 and 300311010. The order called for evaluation of 500,000-sq ft and 1.8-million sq ft industrial scenarios; neither establishes selected final campus design or current title. This is an order for review, not final environmental approval.

Source

Reviewed msp screening context

Source report

The city describes a 300-foot separation between existing residences and project parking, plus an approximately 30-foot berm on the north and east to precede building completion. These are proposed provisions, not verified completed works.

Source

Infrastructure & permits

Technical details (4)
Utility service

Reported context

On-site substation would connect directly to Xcel transmission, not Chaska distribution. System-impact study remains a stated condition.

Cooling system

Reported context

Air-based chillers proposed; anticipated annual water use 14 million gallons, not a measured operating figure.

Fiber

Reported context

Private concrete-encased ducts to telecommunications providers. Adjacent Stream/UnitedHealth sites are separate campuses.

Water supply

Reported context

City describes anticipated 14 million gallons annual water use; proposed, not measured.

Other · Documented

CloudHQ MSP Campus

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.