Cartis diligence evidence schedule

Bridge Data Centres MY07

PRJ-1302 · Site · Ulu Tiram, JHR, Malaysia

Record last updated Oct 29, 2026

Scope and capacity

Bridge Data Centres’ MY07 campus in Ulu Tiram, Johor, is specified for 374 MW of IT capacity across eight buildings on approximately 65 acres. This is full-campus design capacity, not operating load. Changlan reports that its 275 kV cable accessories for the MY07 B1 mechanical/electrical project entered service and connected to TNB’s grid in June 2025, an equipment milestone rather than campus-wide energization. Bridge’s September 2026 account describes active operations and reclaimed water supplying cooling without potable-water reliance. Operating IT capacity, exact parcel title and campus-specific financing remain unverified. MY07 is separate from MY06 at Sedenak.

Headline: 374 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Design IT capacity MW · 374 MW

Design · Bridge Data Centres MY07 (Project)

Claim 160832 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Malaysia

    Bridge Data Centres · Document date: Not stated · Primary

    Source reference: SRC-8145 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.bridgedatacentres.com/locations/malaysia/

Site location · Ulu Tiram, Johor, Malaysia, approximately 65 acres. Prefer the operator’s locality over conflicting secondary Pasir Gudang labels.

Reported rounded · Bridge Data Centres MY07 (Project)

Claim 160833 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Building Malaysia’s Digital Future

    Bridge Data Centres · Document date: Sep 2, 2026 · Corroborating

    Source reference: SRC-8147 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.bridgedatacentres.com/building-malaysias-digital-future/

  2. Bridge Data Centres: Malaysia’s First Data Centre to Apply Effluent Water and Cooling Technologies at Johor’s First Water Reclamation Plant

    Bridge Data Centres · Document date: Sep 2, 2025 · Primary

    Source reference: SRC-8146 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.bridgedatacentres.com/bridge-data-centres-malaysias-first-data-centre-to-apply-effluent-water-and-cooling-technologies-at-johors-first-water-reclamation-plant/

Land and site control context · Operator specifies 65 acres. Secondary parcel and Paragon transaction leads were not primary verified; no parcel/title/price is accepted.

Reported rounded · Bridge Data Centres MY07 (Project)

Claim 160834 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Building Malaysia’s Digital Future

    Bridge Data Centres · Document date: Sep 2, 2026 · Primary

    Source reference: SRC-8147 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.bridgedatacentres.com/building-malaysias-digital-future/

Reviewed b1 cable equipment milestone · In its 2025 ESG report, Changlan says the 275 kV cable accessories it supplied for the BDC MY07 B1 mechanical/electrical project entered service and connected to TNB’s main grid in June 2025. This is a supplier reported equipment milestone, not proof of B1 opening, whole campus energization or any operating IT capacity.

Actual · Bridge Data Centres MY07 (Project)

Claim 162657 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. 2025 Environmental, Social and Governance (ESG) Report

    Changlan · Document date: Not stated · Primary

    Source reference: SRC-8335 · Company announcement · Recorded authority: Party primary

    Source URL

    https://static.cninfo.com.cn/finalpage/2026-03-31/1225059168.PDF

Counterparties and capital

Bridge Data Centres · Developer, Operator · CMP-1384