EverWind Point Tupper Data Centre Campus

Point Tupper, Nova Scotia, CanadaProposed
Evidence
Planned / design
420 MW
Updated
Oct 29, 2026

EverWind proposes a 420 MW campus at Point Tupper, Nova Scotia, comprising 95 MW initially and a later 325 MW expansion; the electrical basis is not explicitly IT load. The developer targets late 2027 and 2028, subject to conditions, and says initial grid studies are complete, not that service is energized. Planned campus investment exceeds CAD8 billion, separate from CAD2 billion for wind. Its FAQ names Anthropic in joint ratepayer commitments. On 20 October 2026, Membertou said it had not partnered in or invested in the campus. Full expansion approval, campus financing close and specialist operating partners remain unverified.

Capacity

Planned campus capacity MW

Planned / design or future potential

420 MW

Source

Initial phase capacity MW

Planned / design or future potential

95 MW

Source

Later phase capacity MW

Planned / design or future potential

325 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (3)
420 MW two-phase campus announced, including initial-phase long-term tenant lease.

Oct 16, 2026 · Recorded actual event

Completed · Announced

Sources (1)
Initial 95 MW phase target, subject to conditions.

Q4 2027 · Forecast / planned record

Forecast · Announced

Sources (1)
Additional 325 MW phase target, not approved/operating capacity.

2028 · Forecast / planned record

Forecast · Announced

Sources (1)

Site & development

Site location

Reported rounded

EverWind owned, previously developed land inside Point Tupper Heavy Industrial Park. Exact data center parcel boundary and street address have not been disclosed in inspected pages.

Source

Land and site control context

Reported rounded

Operator identifies its owned brownfield industrial land, but no title record or exact data center footprint independently recovered.

Source

Additional project facts

Reviewed dated indigenous participation clarification

Actual

On 20 October 2026, Membertou stated that it was not partnered in, and had not invested in, the data centre project at that time. Its wind project partnership is separate. EverWind’s 16 October announcement and current FAQ describe campus stake negotiations, not a completed investment.

Source

Reviewed named AI relationship context

Actual

EverWind’s FAQ names Anthropic in joint ratepayer commitments, and Membertou’s 20 October statement describes the announced Anthropic relationship. This supports attributed relationship context, not verified lease duration, ownership or a specialist operating role.

Source

Infrastructure & permits

Technical details (4)
Electric grid

Reported context

Initial interruptible grid service; battery and emergency-generation support. No claimed operational renewable percentage.

Cooling system

Reported context

Closed-loop water-glycol, predominantly air heat rejection with hot-weather water assistance. Not zero-water cooling.

Fiber

Reported context

Existing industrial-site fiber connectivity described; carrier names and redundant route details not disclosed.

Onsite generation

Reported context

Battery and emergency generation support are planned for interruptible initial grid service. No operating generation capacity is asserted.

Public-source research. Plans may change. See Evidence for sources and qualifications.