atNorth FIN05 Salo

Salo, FinlandProposed
Evidence
Planned critical IT
160 MW
Updated
Oct 29, 2026

atNorth plans FIN05 on a 28.6-hectare site in Kärkkä, Salo. The design provides up to 160 MW IT within a 230 MW gross-power plan; the first phase targets 60 MW IT with 75 MW of power reported secured and power availability forecast for Q3 2028. Salo reports selling approximately seven hectares to Regant DC1 Oy, only part of the campus. Its August 2026 decision approved €3,489,400 sale terms for four city-owned property portions. The operator’s roughly €2 billion investment estimate excludes customer servers and installation and is not committed financing. Construction start, whole-campus title and permit details remain unverified.

Capacity

Target IT capacity MW

Planned / design or future potential

160 MW

Source

Planned gross power capacity MW

Planned / design or future potential

230 MW

Source

First phase target IT capacity MW

Planned / design or future potential

60 MW

Source

First phase secured power capacity MW

Planned / design or future potential

75 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Milestones (2)
FIN05 development announced

Oct 5, 2026 · Recorded actual event

Completed · Announced

Sources (1)
First-phase power availability target in Q3 2028, not energization evidence

Q3 2028 · Forecast / planned record

Forecast · Announced

Sources (1)

Participants

atNorth

Developer · Operator

Sources by role
Developer / Operator (1)

Capital & incentives

Capital claims

Reviewed salo municipal sale terms

Reported rounded

Salo’s 10 August 2026 decision (§260) authorized sale of portions of properties 734-417-1-82, 734-417-1-84, 734-432-4-0 and 734-16-9901-0. The city’s 5 October release reports the approximately seven hectare transaction occurred the preceding week. The approved €3,489,400 price concerns these city portions only; the executed deed and whole campus title were not inspected.

Source

Site & development

Site location

Reported rounded

One 28.6-hectare campus in Kärkkä. Municipality sold roughly seven hectares to Regant DC1 Oy; that transaction is only part of the wider site, not an additional campus.

Source

Land and site control context

Reported rounded

Municipal release says land sale to Regant DC1 occurred the preceding week; preliminary agreement dates to July 2025.

Source

Infrastructure & permits

Technical details (3)
Electric grid

Reported context

Connection planned through a Fingrid substation. Long-term local PPAs are intended, not signed contracts established here.

Cooling system

Reported context

Heat reuse is being explored; no completed heat customer agreement or exact cooling architecture established.

Fiber

Reported context

Operator cites regional connectivity, without named carriers or route count.

Public-source research. Plans may change. See Evidence for sources and qualifications.