AI data center sites

Search sites, programs and supporting energy records by location, company, status or capacity.

1,114 public records · About catalogue coverage

Search property-level records across markets, participants, capacity, development activity, infrastructure and supporting evidence.

1,043 site records69 program records2 energy assets / agreements1,105 detailed profiles9 sourced research records

Record types partition the public catalogue; detailed and sourced-research labels describe those same records, not additional sites. Site records are not a deduplicated count of physical campuses. Overlapping campus, phase or tenant scopes must not be added together.

Site and program directory

1,114 results · Page 13 of 23
Capacity stages and scopes differ; do not add figures together. How to compare

726 of 1114 matching records have an eligible headline. Select both basis and stage for a like-for-like view. Bounds, physical scope and reporting dates still differ; this is not an additive capacity total.

Iron Mountain VA-1 Northern Virginia Data CenterSite · Connected record
Manassas, Virginia, United States
Iron Mountain Data Centers
Operating
12.4 MW
Basis: Critical ITPlanned critical IT
Iron Mountain Data Centers
Oct 28, 2026
Iron Mountain VA-2 Northern Virginia Data CenterSite · Connected record
Manassas, Virginia, United States
Iron Mountain Data Centers
Operating
36 MW
Basis: Critical ITPlanned critical IT
Iron Mountain Data Centers
Oct 28, 2026
Iron Mountain WPA-1 Western Pennsylvania Data CenterSite · Connected record
Boyers, Pennsylvania, United States
Iron Mountain Data Centers
Operating
15.5 MW
Basis: Critical ITPlanned critical IT
Iron Mountain Data Centers
Oct 28, 2026
iXAfrica NBOX1 Nairobi CampusSite · Connected record
Mombasa Road, Nairobi, Kenya
Helios Investment PartnersiXAfrica Data Centres
Partially operational
Not establishedIn published records
iXAfrica Data Centres
Oct 28, 2026
iXAfrica NBOX1.1Site · Connected record
Mombasa Road, Nairobi, Kenya
Operating
Not establishedIn published records
—
Oct 28, 2026
iXAfrica NBOX1.2Site · Connected record
Mombasa Road, Nairobi, Kenya
Preconstruction
Not establishedIn published records
—
Oct 28, 2026
iXAfrica NBOX2 Tilisi CampusSite · Connected record
Tilisi, Greater Nairobi, Kenya
iXAfrica Data Centres
Proposed
Not establishedIn published records
iXAfrica Data Centres
Oct 28, 2026
Joliet Technology CenterSite · Connected record
Joliet, Illinois, United States
Hillwood Development Company
Proposed
1,800 MW
Basis: Basis not specifiedPlanned / design
Hillwood Development Company
Oct 28, 2026
JUPITER Exascale Supercomputer CampusSite · Connected record
Jülich, North Rhine-Westphalia, Germany
EuroHPC Joint UndertakingEviden
Operating
Not establishedIn published records
EuroHPC Joint Undertaking
Oct 28, 2026
Kahla ProjectSite · Connected record
Marquez, Texas, United States
Belltown Power
Proposed
Not establishedIn published records
Belltown Power
Oct 28, 2026
Kairos Hermes 2 Demonstration PlantSite · Connected record
Oak Ridge, Tennessee, United States
GoogleKairos Power LLC
Construction
Not establishedIn published records
Kairos Power LLC
Oct 28, 2026
Kairos Oak Ridge Reactor Demonstration CampusSite · Connected record
Oak Ridge, Tennessee, United States
City of Oak RidgeKairos Power LLC
Construction
Not establishedIn published records
Kairos Power LLC
Oct 28, 2026
Kakao Data Center AnsanSite · Connected record
Ansan, Gyeonggi-do, South Korea
Hanyang University ERICAKakao Corp.
Operating
20 MW
Basis: Critical ITPlanned critical IT
Kakao Corp.
Oct 28, 2026
Kao Data Harlow CampusSite · Connected record
Harlow, England, United Kingdom
Kao Data
Partially operational
71 MW
Basis: Critical ITPlanned critical IT
Kao Data
Oct 28, 2026
Kao Data KLON-05 Northolt Data CenterSite · Connected record
Northolt, England, United Kingdom
Kao Data
Operating
4 MW
Basis: Critical ITPlanned critical IT
Kao Data
Oct 28, 2026
Kao Data KLON-06 Slough Data CenterSite · Connected record
Slough, England, United Kingdom
Kao Data
Operating
20 MW
Basis: Critical ITPlanned critical IT
Kao Data
Oct 28, 2026
Kao Data KMAN-01 Manchester Data CenterSite · Connected record
Stockport, England, United Kingdom
Kao Data
Construction
33 MW
Basis: Critical ITPlanned critical IT
Kao Data
Oct 28, 2026
Kasi Lekki Data Center CampusSite · Connected record
Maiyegun, Lekki, LA, Nigeria
Kasi Cloud DatacentersLagos State Government
Construction
100 MW
Basis: Basis not specifiedPlanned / design
Kasi Cloud Datacenters
Oct 28, 2026
Kasi LOS1Site · Connected record
Maiyegun, Lekki, LA, Nigeria
Kasi Cloud DatacentersTransmission Company of Nigeria
Construction
32 MW
Basis: Basis not specifiedPlanned / design
Kasi Cloud Datacenters
Oct 28, 2026
Keel Sherbrooke AI Data Center CampusSite · Connected record
Sherbrooke, Quebec, Canada
Hydro-SherbrookeKeel Infrastructure
Permitted
96 MW
Basis: Utility / grid serviceUtility capacity
Keel Infrastructure
Oct 28, 2026
Keppel–DDSP Westwood Taiwan Data CenterSite · Connected record
A-Top Cloud Data Park, Taoyuan, TAO, Taiwan
AAM Ruiya Investment Group / A-Top Cloud Data ParkDigital Decarbonization Solutions Platform
Permitted
80 MW
Basis: Basis not specifiedPlanned / design
AAM Ruiya Investment Group / A-Top Cloud Data Park
Oct 28, 2026
Khazna Başkent AI Data CenterSite · Connected record
Ankara, Türkiye
Khazna Data Centers
Preconstruction
100 MW
Basis: Basis not specifiedPlanned / design
Khazna Data Centers
Oct 28, 2026
Khazna Dammam AI-Ready CampusSite · Connected record
Dammam, Eastern Province, Saudi Arabia
Khazna Data Centers
Preconstruction
Up to 200 MW
Basis: Basis not specifiedPlanned / design
Khazna Data Centers
Oct 28, 2026
Khazna QAJ01 Ajman AI Data CenterSite · Connected record
Ajman, AJ, United Arab Emirates
Etihad Water and ElectricityG42
Construction
100 MW
Basis: Critical ITPlanned critical IT
G42
Oct 28, 2026
Khazna-Eni Ferrera Erbognone AI CampusSite · Connected record
Ferrera Erbognone, Lombardy, Italy
Government of the United Arab EmiratesItalian Ministry of Enterprises and Made in Italy
Preconstruction
500 MW
Basis: Critical ITPlanned critical IT
Khazna Data Centers
Oct 28, 2026
Khazna-Eni Italy Data Center ProgramProgram · Connected record
Italy
Khazna Data CentersMGX
Status under review
Not establishedIn published records
Khazna Data Centers
Oct 28, 2026
La Porte Data CenterSite · Connected record
La Porte, Indiana, United States
Microsoft
Preconstruction
538 MW
Basis: Basis not specifiedPlanned / design
Microsoft
Oct 28, 2026
Lefdal Mine Data CenterSite · Connected record
Lefdal near Måløy, Nordfjord, Vestland, Norway
BNP ParibasColumbia Threadneedle European Sustainable Infrastructure Fund
Partially operational
90 MW
Basis: Critical ITPlanned critical IT
Lefdal Mine Data Centers
Oct 28, 2026
LightEdge Kansas City Data CenterSite · Connected record
Kansas City, Missouri, United States
LightEdge
Operating
2.7 MW
Basis: Critical ITPlanned critical IT
LightEdge
Oct 28, 2026
LightEdge Omaha Data CenterSite · Connected record
Papillion, Nebraska, United States
LightEdge
Operating
1.6 MW
Basis: Critical ITPlanned critical IT
LightEdge
Oct 28, 2026
LightEdge Raleigh Data CenterSite · Connected record
Raleigh, North Carolina, United States
LightEdge
Operating
0.2 MW
Basis: Critical ITPlanned critical IT
LightEdge
Oct 28, 2026
Logan Prairie Data CenterSite · Connected record
Latham, Illinois, United States
Hut 8
Delayed
500 MW
Basis: Basis not specifiedPlanned / design
Hut 8
Oct 28, 2026
LOGOS–UEM Gerbang Nusajaya CampusSite · Connected record
Gerbang Nusajaya / Iskandar Puteri, JHR, Malaysia
ESR Group
Cancelled
Not establishedIn published records
ESR Group
Oct 28, 2026
Magnora Hämeenlinna AI Data CenterSite · Connected record
Hämeenlinna, Kanta-Häme, Finland
Magnora Data Center
Preconstruction
120 MW
Basis: Basis not specifiedPlanned / design
Magnora Data Center
Oct 28, 2026
MARA Long Ridge AI Data Center CampusSite · Connected record
Hannibal, Ohio, United States
MARA Holdings
Preconstruction
200 MW
Basis: Utility / grid serviceUtility capacity
MARA Holdings
Oct 28, 2026
MC Digital Realty NRT CampusSite · Connected record
Inzai, Chiba, Japan
Operating
Not establishedIn published records
—
Oct 28, 2026
MC Digital Realty NRT10Site · Connected record
Inzai, Chiba, Japan
Operating
Not establishedIn published records
—
Oct 28, 2026
MC Digital Realty NRT12Site · Connected record
Inzai, Chiba, Japan
Operating
Not establishedIn published records
—
Oct 28, 2026
MC Digital Realty NRT14Site · Connected record
Inzai, Chiba, Japan
Operating
Not establishedIn published records
—
Oct 28, 2026
MEEZA M-Vault 6 Um Garn CampusSite · Connected record
Um Garn, Qatar
MEEZA QSTP-LLC
Construction
24 MW
Basis: Basis not specifiedPlanned / design
MEEZA QSTP-LLC
Oct 28, 2026
MEEZA M-Vault 7 QSTPSite · Connected record
Qatar Science and Technology Park, Doha, Qatar
MEEZA QSTP-LLCQatar Science and Technology Park
Preconstruction
Not establishedIn published records
MEEZA QSTP-LLC
Oct 28, 2026
MEEZA Qatar Data Center Expansion ProgramProgram · Connected record
Qatar
Dukhan BankMEEZA QSTP-LLC
Status under review
Not establishedIn published records
MEEZA QSTP-LLC
Oct 28, 2026
Merom Generating Station Data Center ConversionSite · Connected record
Merom, Indiana, United States
Hallador Energy
Preconstruction
Not establishedIn published records
Hallador Energy
Oct 28, 2026
Meta Altoona Data CenterSite · Connected record
Altoona, Iowa, United States
Meta Platforms, Inc.
Operating
Not establishedIn published records
Meta Platforms, Inc.
Oct 28, 2026
Meta Beaver Dam Data CenterSite · Connected record
Alliant Energy Beaver Dam Commerce Park, Beaver Dam, Wisconsin, United States
Alliant Energy / Wisconsin Power and Light CompanyCity of Beaver Dam
Construction
Not establishedIn published records
Degas LLC
Oct 28, 2026
Meta Clonee Data CenterSite · Connected record
Clonee, County Meath, Ireland
Meta Platforms, Inc.
Operating
Not establishedIn published records
Meta Platforms, Inc.
Oct 28, 2026
Meta DeKalb Data CenterSite · Connected record
DeKalb, Illinois, United States
Commonwealth Edison CompanyGoldframe LLC
Operating
Not establishedIn published records
Goldframe LLC
Oct 28, 2026
Meta Eagle Mountain Data CenterSite · Connected record
Eagle Mountain, Utah, United States
Meta
Operating
Not establishedIn published records
Meta
Oct 28, 2026
Meta El Paso Data CenterSite · Connected record
El Paso, Texas, United States
MetaMeta Platforms
Construction
1,000 MW
Basis: Critical ITPlanned critical IT
Meta
Oct 28, 2026
Meta Forest City Data CenterSite · Connected record
Forest City, North Carolina, United States
Meta Platforms, Inc.
Operating
Not establishedIn published records
Meta Platforms, Inc.
Oct 28, 2026

Every figure carries its capacity stage. Operating, contracted, planned/design and utility-service values remain distinct; generation is never used as site capacity. A missing figure does not mean zero; other scoped figures may appear in the profile.