Skip to content

Kao Data KLON-06 Slough Data Center

Slough, England, United KingdomOperating
Evidence
Planned critical IT
20 MW
Updated
Oct 28, 2026

KLON-06 is Kao Data’s operating Slough facility. A contractor project record independently confirms four expansion phases that added 12 MW within a live site, supporting the current 20 MW facility boundary while preserving the distinction between installed capacity and utilization. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Capacity

Reported capacity

Design

20 MW

Source

Reported capacity

Design

20 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

KLON-06 is Kao Data’s operating Slough facility. A contractor project record independently confirms four expansion phases that added 12 MW within a live site, supporting the current 20 MW facility boundary while preserving the distinction between installed capacity and utilization. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Milestones (1)
Contractor record confirms four live-site expansion phases complete

Aug 29, 2026 · Recorded actual event

Completed · Status changed

Source not linked

Participants

Kao Data

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

KLON-06 | Slough | England | GB

Source

Location context

Actual

KLON-06 | Slough | England | GB

Source

Additional project facts

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

Kao Data currently publishes 20 MW operational capacity for KLON-06.

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

20 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Source

Operator confirmed

Actual

Kao Data

Source

Facility capacity basis

Actual

20 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Source

Current lifecycle

Actual

Operating

Source

Expansion phase count

Actual

4 phases

Source

Infrastructure & permits

Technical details (2)
Electric grid

Operational

20 MW

Facility IT boundary; customer utilization is not disclosed.

Fiber

Operational

Carrier-neutral or resilient fibre connectivity described for the individual facility.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (4)
CyrusOne LON1 Slough Data Center

Operating · Slough, England, United Kingdom

Same locality: Slough

Compare in a collection
CyrusOne LON3 Slough Data Center

Operating · Slough, England, United Kingdom

Same locality: Slough

Compare in a collection
CyrusOne LON4 Slough Data Center

Operating · Slough, England, United Kingdom

Same locality: Slough

Compare in a collection
CyrusOne LON5 Slough Data Center

Operating · Slough, England, United Kingdom

Same locality: Slough

Compare in a collection