Skip to content
All records
Data center siteSite record

Kao Data KLON-06 Slough Data Center

Slough, England, United KingdomOperating / Stabilized
Capacity
20 MW
Planned critical IT
Lead participant
Kao Data
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Kao Data KLON-06 Slough Data Center

KLON-06 is Kao Data’s operating Slough facility. A contractor project record independently confirms four expansion phases that added 12 MW within a live site, supporting the current 20 MW facility boundary while preserving the distinction between installed capacity and utilization. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load20 MWDesign · Kao Data KLON-06 Slough Data Center
It Load20 MWDesign · Kao Data KLON-06 Slough Data Center

Development

1 phases · 2 milestones
Operating facility and documented expansionOperational

KLON-06 is Kao Data’s operating Slough facility. A contractor project record independently confirms four expansion phases that added 12 MW within a live site, supporting the current 20 MW facility boundary while preserving the distinction between installed capacity and utilization. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Aug 29, 2026
Project-specific source review refreshed
Completed
Aug 29, 2026
Contractor record confirms four live-site expansion phases complete
Completed

Infrastructure

Electric GridOperational

20 MW

Facility IT boundary; customer utilization is not disclosed.

FiberOperational

Carrier-neutral or resilient fibre connectivity described for the individual facility.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

13 facts
Location Context
KLON-06 | Slough | England | GB
Actual
Lifecycle Status
Operating
Actual
Reported Capacity
20 MW
Design
Capacity Basis
Kao Data currently publishes 20 MW operational capacity for KLON-06.
Actual
Location Context
KLON-06 | Slough | England | GB
Actual
Lifecycle Status
Operating
Actual
Reported Capacity
20 MW
Design
Capacity Basis
20 MW is the operator published facility IT-load boundary; it is not measured customer utilization.
Actual
Operator Confirmed
Kao Data
Actual
Facility Capacity Basis
20 MW is the operator published facility IT-load boundary; it is not measured customer utilization.
Actual
Current Lifecycle
Operating
Actual
Evidence Boundary
Facility specific evidence; campus or portfolio figures are not transferred between records
Actual
Expansion Phase Count
4 phases
Actual