Headline capacity
Not established in published records
Updated
Oct 28, 2026

M-Vault 7 is MEEZA's planned 16 MW data center at Qatar Science and Technology Park. It reached final design by February 2026 and remained in continued development at the end of June 2026.

Program relationships

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

M-Vault 7 design and construction startAnnounced or preconstruction

1 building

A calendar-year construction target is not an achieved start.

Milestones (2)
M-Vault 7 reaches final design stage

Feb 23, 2026 · Recorded actual event

Completed · Status changed

Source not linked
M-Vault 7 construction-start target

2026 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

MEEZA QSTP-LLC

Operator

Sources by role
Operator (1)
Operator (1)
Qatar Science and Technology Park

Landowner

Sources by role
Landowner (1)

Site & development

Location

Actual

Qatar Science and Technology Park, Doha, Qatar

Source

Construction start

Forecast

Later in 2026

M-Vault 7 design and construction start · Phase

Source

Additional project facts

Status

Actual

Final stages of design

M-Vault 7 design and construction start · Phase

Source

Status

Actual

Continued development

Source

Boundary exclusion

Actual

M-Vault 4 expansion, M-Vault 6 and M-Vault 8 are separate facilities

Source

Infrastructure & permits

Technical details (1)
Electric grid

Planned or represented

16 MW

Design capacity; source does not define IT versus utility basis.