MEEZA Qatar Data Center Expansion Program
- Headline capacity
- See constituent sites
- Updated
- Oct 28, 2026
MEEZA is financing a three-facility Qatar expansion expected to add about 44 MW across M-Vaults 6-8. MEEZA Qatar Data Center Expansion Program is located in Qatar, QA and is a program in construction status.
Constituent sites / phases
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Portfolio target from the H1 2026 release; facility allocations are not disclosed.
Milestones (5)
Aug 26, 2025 · Recorded actual event
Completed · Financing
Source not linkedOct 28, 2025 · Recorded actual event
Completed · Customer commitment
Source not linkedJul 28, 2026 · Recorded actual event
Completed · Status changed
Source not linkedJul 30, 2026 · Recorded actual event
Completed · Financing
Source not linkedJul 30, 2026 · Recorded actual event
Completed · Financing
Source not linkedParticipants
Developer · Investor
Sources by role
Developer (1)
- MEEZA secures additional QAR 1.6 billion Murabaha facility · Jul 30, 2026 · Primary
Developer (1)
- MEEZA secures QAR 800 million Commodity Murabaha facility · Aug 26, 2025 · Corroborating
Investor (1)
- MEEZA secures additional QAR 1.6 billion Murabaha facility · Jul 30, 2026 · Corroborating
Investor (1)
- MEEZA records 15% revenue growth during H1 2026 · Jul 28, 2026 · Primary
Customer
Sources by role
Customer (1)
- MEEZA signs QAR 750 million-plus 6 MW hyperscaler agreement · Oct 28, 2025 · Primary
Other participants (1)
Lender
Sources by role
Lender (1)
- MEEZA secures additional QAR 1.6 billion Murabaha facility · Jul 30, 2026 · Primary
Lender (1)
- Dukhan Bank confirms MEEZA QAR 800 million facility · Aug 26, 2025 · Corroborating
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Commodity Murabaha facility
QAR 800,000,000Aug 26, 2025
Portfolio facility for 44 MW expansion; no project-cost allocation.
Parties & sources
Dukhan Bank (Lender) · MEEZA QSTP-LLC (Borrower)
Sources (2)
- MEEZA secures QAR 800 million Commodity Murabaha facility · Aug 26, 2025
- Dukhan Bank confirms MEEZA QAR 800 million facility · Aug 26, 2025
Customer data center lease
QAR 750,000,000Oct 28, 2025
More-than amount for 6 MW phase; customer and exact campus undisclosed.
Parties & sources
MEEZA QSTP-LLC (Service provider) · Undisclosed MEEZA hyperscaler customer (Customer)
Sources (1)
- MEEZA signs QAR 750 million-plus 6 MW hyperscaler agreement · Oct 28, 2025
Additional Commodity Murabaha facility
QAR 1,600,000,000Jul 30, 2026
Additional portfolio facility covering M-Vaults 6-8;
Parties & sources
Dukhan Bank (Lender) · MEEZA QSTP-LLC (Borrower)
Sources (1)
- MEEZA secures additional QAR 1.6 billion Murabaha facility · Jul 30, 2026
Debt financing
QAR 1,600,000,000Jul 30, 2026
Additional facility from Dukhan Bank supports M-Vault 6, 7 and 8 and broader portfolio growth; no amount is allocated to M-Vault 7.
Parties & sources
Dukhan Bank (Lender) · MEEZA QSTP-LLC (Borrower)
Sources (1)
- MEEZA secures additional QAR 1.6 billion Murabaha facility · Jul 30, 2026
Additional project facts
Infrastructure & permits
Technical details (1)
Planned or represented
60 MW
More than 60 MW over three years; 60 is stored with a greater-than qualifier in assertions and is not allocated across facilities.
Constituent-site map
Public-source research. Plans may change. See Evidence for sources and qualifications.