MEEZA Qatar Data Center Expansion Program

QatarStatus under reviewProgram
Evidence
Headline capacity
See constituent sites
Updated
Oct 28, 2026

MEEZA is financing a three-facility Qatar expansion expected to add about 44 MW across M-Vaults 6-8. MEEZA Qatar Data Center Expansion Program is located in Qatar, QA and is a program in construction status.

Constituent sites / phases

Capacity

Planned additional capacity

Planned / design or future potential

44 MW

Source

Capacity target

Planned / design or future potential

60 MW+

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Three-year Qatar capacity expansionOperational

Portfolio target from the H1 2026 release; facility allocations are not disclosed.

Milestones (5)
First expansion facility signed

Aug 26, 2025 · Recorded actual event

Completed · Financing

Source not linked
Unnamed hyperscaler agreement signed

Oct 28, 2025 · Recorded actual event

Completed · Customer commitment

Source not linked
MEEZA confirms continued expansion

Jul 28, 2026 · Recorded actual event

Completed · Status changed

Source not linked
Second expansion facility signed

Jul 30, 2026 · Recorded actual event

Completed · Financing

Source not linked
MEEZA secures program financing

Jul 30, 2026 · Recorded actual event

Completed · Financing

Source not linked

Participants

MEEZA QSTP-LLC

Developer · Investor

Sources by role
Developer (1)
Developer (1)
Investor (1)
Investor (1)
Other participants (1)
Dukhan Bank

Lender

Sources by role
Lender (1)
Lender (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Facilities financed

Actual

M-Vault 6; M-Vault 7; M-Vault 8

Source

Financing amount

Transaction scope

1,600,000,000 QAR

Source

Financing instrument

Transaction scope

Long term Sharia compliant Commodity Murabaha

Source

Financing records

Commodity Murabaha facility

QAR 800,000,000

Aug 26, 2025

Portfolio facility for 44 MW expansion; no project-cost allocation.

Parties & sources

Dukhan Bank (Lender) · MEEZA QSTP-LLC (Borrower)

Customer data center lease

QAR 750,000,000

Oct 28, 2025

More-than amount for 6 MW phase; customer and exact campus undisclosed.

Parties & sources

MEEZA QSTP-LLC (Service provider) · Undisclosed MEEZA hyperscaler customer (Customer)

Additional Commodity Murabaha facility

QAR 1,600,000,000

Jul 30, 2026

Additional portfolio facility covering M-Vaults 6-8;

Parties & sources

Dukhan Bank (Lender) · MEEZA QSTP-LLC (Borrower)

Debt financing

QAR 1,600,000,000

Jul 30, 2026

Additional facility from Dukhan Bank supports M-Vault 6, 7 and 8 and broader portfolio growth; no amount is allocated to M-Vault 7.

Parties & sources

Dukhan Bank (Lender) · MEEZA QSTP-LLC (Borrower)

Additional project facts

Named expansion facilities

Actual

3 facilities

Source

Additional murabaha facility

Actual

1.6 QAR billion

Source

Prior murabaha facility

Actual

800 QAR million

Source

Hyperscaler contract value over

Actual

750 QAR million

Source

Included facilities

Actual

M-Vault 6; M-Vault 7; M-Vault 8

Source

Target horizon

Forecast

3 years

Source

Infrastructure & permits

Technical details (1)
Electric grid

Planned or represented

60 MW

More than 60 MW over three years; 60 is stored with a greater-than qualifier in assertions and is not allocated across facilities.

Public-source research. Plans may change. See Evidence for sources and qualifications.