Data center siteSite record

Keppel–DDSP Westwood Taiwan Data Center

A-Top Cloud Data Park, Taoyuan, TAO, TaiwanEntitled / Permitted

Location note: exact parcel not disclosed

Capacity
80 MW
Planned / design
Lead participant
AAM Ruiya Investment Group / A-Top Cloud Data Park
Developer
Last updated
Aug 22, 2026
Most recent public record update

About Keppel–DDSP Westwood Taiwan Data Center

Keppel Data Centre Fund II and DDSP are developing Westwood, an 80 MW two-phase campus inside A-Top Cloud Data Park in Taoyuan. Phase 1 is about 30 MW, contracted to an undisclosed cloud provider and supported by a June 2026 Nomura financing.

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design80 MWDesign · Keppel–DDSP Westwood Taiwan Data Center
Design30 MWDesign · Phase 1 / first building

Development

3 phases · 4 milestones
Westwood / Taiwan DC Campus full buildPlanned

Full project inside A-Top; excludes other park facilities.

Phase 1 / first buildingAnnounced Or Preconstruction

Approximately 30 MW reported in 2025; Q1 2026 opening target unconfirmed.

1 building

Phase 2Planned

No phase capacity or date published separately.

Oct 21, 2024
KDCF II and DDSP announced Taiwan DC Campus
Completed
Mar 26, 2025
A-Top/CNA identified Westwood and ~30 MW Phase 1
Completed
Mar 31, 2026
Phase 1 activation target passed without operating confirmation
Forecast
Jun 8, 2026
Nomura financing transaction completed
Completed

Infrastructure

Electric GridSecured Or Contracted

grid power connection; permitted and power secured.

Utility ServiceReported Context

parent park energy and storage; external plan.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 2

Facts & sources

Published claims and their source links.

10 facts
Project Status
Permitted, power secured, contracted and Phase 1 financed
Transaction Scope
Total Capacity
80 MW
Design
Resilience Design
Tier III-equivalent
Design
Phase Count
2 phases
Design
Phase Capacity
30 MW
Design
Anchor Contract
Long term contract with leading global cloud/hyperscale customer
Actual
Joint Venture Ownership
KDCF II 50%; DDSP 50%
Actual
Municipality
Taoyuan
Reported Rounded
Parent Data Park
A-Top Cloud Data Park
Actual
Financing Status
Nomura financing transaction completed; amount undisclosed
Closed Financing