Khazna QAJ01 Ajman AI Data Center

Ajman, AJ, United Arab EmiratesUnder construction
Evidence
Planned critical IT
100 MW
Updated
Oct 28, 2026
Utility
Etihad Water and Electricity

Khazna is building QAJ01 in Ajman as a 100 MW AI-optimized data center with twenty planned 5 MW halls. Uptime Institute has certified the design documents, not the completed facility.

Capacity

Designed IT capacity

Planned / design or future potential

100 MW

Source

Designed capacity per hall

Planned / design or future potential

5 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

QAJ01 construction and modular hall programUnder construction

1 building

One facility containing 20 planned data halls; halls are not separate buildings.

Initial operational phasePlanned

Initial-phase MW and commissioned halls are not disclosed.

Milestones (5)
Khazna announces QAJ1 construction

Oct 15, 2024 · Recorded actual event

Completed · Construction started

Source not linked
Structural steel completed

Apr 21, 2025 · Recorded actual event

Completed · Status changed

Source not linked
Original QAJ1 operating target

Q3 2025 · Event timing type not established

Cancelled · Forecast completion

Source not linked
Uptime certifies design documents

Feb 24, 2026 · Recorded actual event

Completed · Status changed

Source not linked
Initial operational phase target

Dec 2026 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

G42

Owner

Sources by role
Khazna Data Centers

Operator

Sources by role
Other participants (2)
Etihad Water and Electricity

Utility provider

Sources by role
Utility provider (1)
Uptime Institute

Contractor

Sources by role

Site & development

Gross floor area

Design

100,000 sqm

Source

Technical specifications

Cooling system

Design

Liquid cooling

Source

Additional project facts

Project status

Actual

Under construction

Source

Planned data halls

Design

20 hall

Source

Initial phase delivery target

Forecast

2026-12

Initial operational phase · Phase

Source

Structural steel status

Actual

Complete

QAJ01 construction and modular hall program · Phase

Source

Tier certification

Design

Tier III Certification of Design Documents

Source

Primary electricity supplier

Actual

Etihad Water and Electricity

Source

Infrastructure & permits

Technical details (4)
Electric grid

Under construction

100 MW

designed it capacity — 100 MW; under construction.

Site facility

Planned or represented

5 MW per hall

5 MW DESIGN IT per modular hall within the 100 MW/20-hall full facility. Hall units are not additive to campus total and not evidence of commissioned halls.

Electric grid

Potential or planned

utility supply; planned or connected unverified.

Cooling system

Under construction

liquid cooling; designed under construction.