Magnora Hämeenlinna AI Data Center

Hämeenlinna, Kanta-Häme, FinlandPreconstruction
Evidence
Planned / design
120 MW
Updated
Oct 28, 2026

Magnora announced on August 24, 2026 a firm grid-connection agreement for Hämeenlinna and a secured building permit, with connection scheduled for Q1 2029 and potentially the second half of 2028. An August 25 announcement confirmed completion of the transaction giving it full project ownership. The grid schedule is not energization. Magnora Data Center is developing an AI-ready project in Hämeenlinna, Finland. Company reporting identifies a 120 MW planned design and an earlier ready-to-build target by the end of 2026. Earlier Magnora reporting described a grid letter of intent, ground lease and building-permit work; the August announcements update the connection and permit position.

Capacity

Reported capacity

Planned / design or future potential

120 MW

Source

Capacity

Planned / design or future potential

120 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development programAnnounced or preconstruction

Magnora Hämeenlinna AI Data Center: Preconstruction.

Milestones (2)
Magnora Hämeenlinna AI Data Center: Development-stage; ready-to-build targeted by end of 2026.

May 1, 2026 · Event timing type not established

In progress · Announced

Source not linked
Magnora Hämeenlinna AI Data Center — Preconstruction

Date not disclosed · Event timing type not established

In progress · Status changed

Source not linked

Participants

Magnora Data Center

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Magnora data center site | Hämeenlinna | Finland

Source

Location

Actual

Hämeenlinna, Kanta-Häme, FI

Source

Development scale

Actual

120 MW planned design; ready to build target by end of 2026.

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

Magnora reports a 120 MW AI-ready design.

Source

Project identity

Actual

Magnora Hämeenlinna AI Data Center

Source

Lifecycle status

Actual

Preconstruction

Source

Participant roles

Actual

Magnora Data Center

Source

Capacity basis

Actual

120 MW planned or design IT capacity

Source

Infrastructure

Actual

Grid letter of intent, ground lease and building permit work reported by Magnora.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

120 MW

120 MW planned or design IT capacity

Site facility

Planned or represented

Grid letter of intent, ground lease and building-permit work reported by Magnora.

Public-source research. Plans may change. See Evidence for sources and qualifications.