Merom Generating Station Data Center Conversion
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
Hallador is evaluating new gas generation at the operating Merom power site to serve utility and data center demand; this is not yet a completed data center conversion. The company acquired roughly 460 MW of Siemens equipment for $350 million and expects a final investment decision only after interconnection, offtake, financing and permitting work.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Hallador is evaluating new gas generation at the operating Merom power site to serve utility and data center demand; this is not yet a completed data center conversion. The company acquired roughly 460 MW of Siemens equipment for $350 million and expects a final investment decision only after interconnection, offtake, financing and permitting work.
Milestones (2)
Dec 2025 · Recorded actual event
Completed · Permit filed
Source not linkedJun 1, 2026 · Recorded actual event
Completed · Equipment deployment
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Merom Generating Station Data Center Conversion project source · Aug 28, 2026 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
$350mJun 1, 2026
Siemens turbine and generator equipment
Parties & sources
Hallador Energy (Borrower)
Sources (1)
- Hallador acquires turbines for Merom project · Jun 1, 2026
Site & development
Additional project facts
Capacity basis
Actual1,080 MW onsite generation; not measured operating IT load. The 1,080 MW value is the generating station rating and must not be presented as data center IT capacity.
SourceInfrastructure & permits
Technical details (2)
Planned or represented
1,080 MW
Existing station rating; not data center IT load.
Planned or represented
460 MW
New Siemens equipment subject to final investment decision.