Lefdal Mine Data Center
- Planned critical IT
- 90 MW
- Updated
- Oct 28, 2026
Lefdal Mine Data Center operates inside a former mine near Måløy and is expanding data halls across a six-level, 75-chamber campus. The site reports 10 MW in operation, 20 MW reserved for customers, 80 MW available power and up to 200 MW potential, alongside fjord-water cooling and renewable electricity.
Capacity
Power potential
Planned / design or future potentialUp to 200 MW
Full mine potential · Phase
Phase scope; not a whole-site figure
SourceAdded power capacity
Actual60 MW
80 MW available-power expansion · Phase
Phase scope; not a whole-site figure
SourceFuture cooling capacity
Planned / design or future potential200 MW
Full mine potential · Phase
Phase scope; not a whole-site figure
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Shared mine campus; individual customer halls are deployments, not separately named public facilities.
Electrical availability; 20 MW was reported reserved for current customers and should not be conflated with live IT load.
Customer-triggered halls averaging about 700 m² are built within the mine.
Ultimate physical and electrical potential, not delivered capacity.
Milestones (5)
2017 · Recorded actual event
Completed · Commercial operation
Source not linkedMay 6, 2020 · Recorded actual event
Completed · Financing
Source not linkedNov 5, 2024 · Recorded actual event
Completed · Status changed
Source not linkedOct 13, 2025 · Recorded actual event
Completed · Customer commitment
Source not linkedDate not disclosed · Recorded actual event
Completed · Capacity revised
Source not linkedParticipants
Customer
Sources by role
Customer (1)
- BNP Paribas has selected Lefdal Mine Data Centers to host their HPC capacity needs · Oct 13, 2025 · Primary
Investor
Sources by role
Investor (1)
- Ownership · Primary
Operator
Sources by role
Operator (1)
- Our Facility · Primary
Operator (1)
- Lefdal Mine Data Centers expand power capacity with 60 MW · Corroborating
Customer
Sources by role
Customer (1)
- Daimler is through Infosys moving their HPC cluster to Lefdal Mine Data Centers · Nov 30, 2021 · Primary
Other participants (4)
Supplier
Sources by role
Supplier (1)
- Daimler is through Infosys moving their HPC cluster to Lefdal Mine Data Centers · Nov 30, 2021 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Typical hall investment
Reported roundedNOK 250–300 million
Continuous customer-hall buildout · Phase
SourceFinancing records
Investment commitment
NOK 250,000,000Nov 5, 2024
Operator reports each typical customer hall involves about NOK 250–300 million. This lower-bound record is construction-cost context, not a financing close or amount for every hall.
Parties & sources
Lefdal Mine Data Centers (Other)
Sources (1)
- Lefdal Mine Data Centers create regional development · Nov 5, 2024
Investment commitment
NOK 300,000,000Nov 5, 2024
Upper bound of the same typical-hall investment range; no hall count or funding instrument is inferred.
Parties & sources
Lefdal Mine Data Centers (Other)
Sources (1)
- Lefdal Mine Data Centers create regional development · Nov 5, 2024
Site & development
Technical specifications
Additional project facts
Customer deployment
ActualMercedes/Daimler HPC workloads moved through Infosys Green Data Center as a Service
SourceInfrastructure & permits
Technical details (15)
Reported context
10 MW in operation
Current HPC page statement; distinct from 20 MW reserved and 80 MW available electrical power.
Reported context
20 MW reserved
Reserved for current customers; does not prove simultaneous operating IT draw.
Operational
80 MW available
Available electrical capacity after a 60 MW expansion from 20 MW.
Reported context
80 MW level capacity
Level 3 design statement; not treated as additional to the campus's 80 MW available power.
Planned or represented
200 MW potential
Ultimate mine-campus potential; not delivered or reserved capacity.
Operational
132 kV
Direct connection to the regional grid through operator-owned transformers.
Planned or represented
200 MW
Last-mile grid reinforced for 200 MW with separated entries; transformer installation remains modular.
Operational
90 MW cooling
Twelve modular 7.5 MW heat exchangers on Level 3 total 90 MW cooling.
Planned or represented
200 MW redundant cooling
Next cooling level is intended to support 200 MW redundant capacity.
Reported context
8 degrees C
Year-round seawater source for heat exchangers.
Reported context
100 meters
Redundant piping draws fjord water from about 100 m depth.
Planned or represented
1.08 PUE lower bound
Operator range is 1.08–1.15 depending on cooling technology, UPS configuration and scale; not an observed annual average.
Planned or represented
1.15 PUE upper bound
Upper bound of the operator's configuration-dependent PUE range.
Reported context
50 kW per rack up to
Air-cooling capability; direct liquid and immersion can support higher densities but no normalized ceiling is imported.
Reported context
0 WUE
No evaporative cooling; operator reports WUE zero. Treat as claimed design/operation metric, not independently measured.
Project map
Project map
1 of 1 project point mappedPublic-source research. Plans may change. See Evidence for sources and qualifications.