Kasi Lekki Data Center Campus

Maiyegun, Lekki, LA, NigeriaUnder construction
Evidence
Planned / design
100 MW
Updated
Oct 28, 2026
Utility
Transmission Company of Nigeria

Kasi is developing a carrier-neutral, AI-ready campus in Maiyegun, Lekki. Its first facility has reached commissioning, while the campus's 100 MW figure remains a long-term buildout envelope. Kasi Lekki Data Center Campus is located in Maiyegun, Lekki, LA, NG and is a data center campus in construction status.

Constituent sites / phases

Capacity

Planned campus capacity

Planned / design or future potential

100 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Long-term campus buildoutAnnounced or preconstruction

Campus envelope only; no allocation among future buildings.

Milestones (1)
Kasi broke ground on first Lagos campus

Apr 19, 2022 · Recorded actual event

Completed · Construction started

Source not linked

Participants

Kasi Cloud Datacenters

Developer · Operator

Sources by role
Other participants (2)
Lagos State Government

Government authority

Sources by role
Government authority (1)
Government authority (1)
Transmission Company of Nigeria

Utility provider

Sources by role
Utility provider (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Reported campus investment

Actual

$250 million

Source

Financing records

Reported campus investment

$250m

Apr 19, 2022

Groundbreaking release described a USD 250 million campus; capital structure, draw schedule and current spend remain undisclosed.

Parties & sources

Kasi Cloud Datacenters (Developer / investment recipient) · Nigeria Sovereign Investment Authority (Foundational investor)

Site & development

Site area approximately

Actual

4 hectares

Source

Construction groundbreaking date

Actual

2022-04-19

Source

Additional project facts

Commissioning flag off date

Actual

2026-05-19

Source

Carrier neutral design

Actual

True

Source

Direct tcn connection voltage

Actual

132 kV

Source

Hybrid gas solar battery design

Actual

True

Source

PUE target at most

Actual

1.6

Source

Subsea cable systems adjacent

Actual

6 systems

Source

Infrastructure & permits

Technical details (4)
Electric grid

Under construction

132 kV

Direct TCN connection disclosed; energized service capacity and contracted draw are not public.

Onsite generation

Planned or represented

Hybrid gas and solar generation design; installed capacities are undisclosed.

Battery storage

Planned or represented

Battery storage forms part of hybrid-power and redundancy design; capacity undisclosed.

Fiber

Planned or represented

6 subsea cable systems

Carrier-neutral design adjacent to Equiano, 2Africa and four additional systems; executed carrier agreements undisclosed.

Permit · Status not stated

Kasi Lekki campus

Lagos State Government

Feb 5, 2026

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.