Joliet Technology Center

Joliet, Illinois, United StatesProposed
Capacity
1,800 MW
Planned / design
Lead participant
Hillwood Development Company
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Joliet Technology Center

Joliet Technology Center is Hillwood’s proposed 795-acre data center campus in Joliet, Illinois. Project materials describe a $20 billion, 1.8 GW full-build program over roughly five to seven years, with closed-loop cooling, ComEd service and no planned onsite generation. The city conditionally approved annexation in March 2026, but building permits, utility delivery and construction remain phased. The 1.8 GW figure is a future design objective, not operating capacity.

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential1,800 MWDesign · Joliet Technology Center
Future Potential1,800 MWDesign · Joliet Technology Center

Development

1 phases · 1 milestones
Conditionally approved; phased developmentAnnounced Or Preconstruction

Joliet Technology Center is Hillwood’s proposed 795-acre data center campus in Joliet, Illinois. Project materials describe a $20 billion, 1.8 GW full-build program over roughly five to seven years, with closed-loop cooling, ComEd service and no planned onsite generation. The city conditionally approved annexation in March 2026, but building permits, utility delivery and construction remain phased. The 1.8 GW figure is a future design objective, not operating capacity.

Mar 19, 2026
City approved conditional annexation
Completed

Infrastructure

Electric GridPlanned Or Represented

1,800 MW

ComEd-served full-build concept.

Cooling SystemPlanned Or Represented

Closed-loop cooling; no onsite generation planned.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Joliet Technology Center | Joliet | Illinois | US
Actual
Lifecycle Status
Proposed
Actual
Reported Capacity
1,800 MW
Design
Capacity Basis
1,800 MW future full build site capacity; not measured operating IT load.
Actual
Location Context
Joliet Technology Center | Joliet | Illinois | US
Actual
Lifecycle Status
Proposed
Actual
Reported Capacity
1,800 MW
Design
Capacity Basis
1,800 MW is the proposed full build campus design over a multi year development period.
Actual
Site Area
795 acres
Actual
Reported Investment
$20,000,000,000
Reported Rounded
Buildout Duration
5–7 Years
Actual
Permanent Jobs
700 jobs
Reported Rounded