LOGOS–UEM Gerbang Nusajaya Campus

Gerbang Nusajaya / Iskandar Puteri, JHR, MalaysiaCancelled
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

A proposed UEM Sunrise and LOGOS data-centre campus in Gerbang Nusajaya did not advance beyond an exploratory 2024 MoU. UEM Sunrise said in June 2025 that the partnership had lapsed and it was considering a sale of the 74-acre parcel.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Exclusive exploration MoUChanged or cancelled

30-hectare site and up-to-360 MW development potential were exploratory.

Post-cancellation land marketingAnnounced or preconstruction

Land disposition is an event, not a replacement data-centre project.

Participants

ESR Group

Owner

Sources by role

Additional project facts

Project identity

Source report

LOGOS–UEM Gerbang Nusajaya Campus

Source

Infrastructure & permits

Technical details (1)
Electric grid

Cancelled or not proceeding

360 MW

Original up-to development potential; never verified as IT load, grid allocation or operating capacity.

Public-source research. Plans may change. See Evidence for sources and qualifications.