AI data center sites

Search sites, programs and supporting energy records by location, company, status or capacity.

1,114 public records · About catalogue coverage

Search property-level records across markets, participants, capacity, development activity, infrastructure and supporting evidence.

1,043 site records69 program records2 energy assets / agreements1,105 detailed profiles9 sourced research records

Record types partition the public catalogue; detailed and sourced-research labels describe those same records, not additional sites. Site records are not a deduplicated count of physical campuses. Overlapping campus, phase or tenant scopes must not be added together.

Clear all filters

Site and program directory

524 results · Page 3 of 11
Capacity stages and scopes differ; do not add figures together. How to compare

332 of 524 matching records have an eligible headline. Select both basis and stage for a like-for-like view. Bounds, physical scope and reporting dates still differ; this is not an additive capacity total.

Cipher Milsing AI Data Center CampusSite · Connected record
Texas, United States
Cipher Digital
Proposed
Not establishedIn published records
Cipher Digital
Oct 28, 2026
Cipher Reveille AI Data Center CampusSite · Connected record
Texas, United States
Cipher Digital
Preconstruction
70 MW
Basis: Utility / grid serviceUtility capacity
Cipher Digital
Oct 28, 2026
Cipher Stingray AI Data Center CampusSite · Connected record
Texas, United States
Cipher Digital
Construction
100 MW
Basis: Basis not specifiedContracted
Cipher Digital
Oct 28, 2026
Cipher Ulysses AI Data Center CampusSite · Connected record
Ohio, United States
Cipher Digital
Preconstruction
200 MW
Basis: Utility / grid serviceUtility capacity
Cipher Digital
Oct 28, 2026
CleanArc VA1 CampusSite · Connected record
Ruther Glen, Virginia, United States
CleanArc Data Centers
Preconstruction
900 MW
Basis: Basis not specifiedPlanned / design
CleanArc Data Centers
Oct 28, 2026
CleanCore West Texas AI Data Center CampusSite · Connected record
Texas, United States
CleanCore Solutions
Preconstruction
200 MW
Basis: Basis not specifiedPlanned / design
CleanCore Solutions
Oct 28, 2026
CleanCore–Cerebras Minnesota AI Data CenterSite · Connected record
Minnesota, United States
Cerebras SystemsCleanCore Solutions
Preconstruction
40 MW
Basis: Basis not specifiedContracted
CleanCore Solutions
Oct 28, 2026
CleanSpark Sandersville AI Data Center CampusSite · Connected record
Sandersville, Georgia, United States
CleanSpark
Preconstruction
175 MW
Basis: Basis not specifiedContracted
CleanSpark
Oct 28, 2026
CloudBurst Texas Flagship CampusSite · Connected record
Texas, United States
CloudBurst Data Centers
Preconstruction
1,200 MW
Basis: Critical ITPlanned critical IT
CloudBurst Data Centers
Oct 28, 2026
Cloverleaf Infrastructure Troy CampusSite · Connected record
Troy, Illinois, United States
Cloverleaf Infrastructure
Proposed
500 MW
Basis: Basis not specifiedPlanned / design
Cloverleaf Infrastructure
Oct 28, 2026
College Station 600-MW Data Center ProposalSite · Connected record
College Station, Texas, United States
City of College StationPriority Power Management, LLC
Cancelled
600 MW
Basis: Basis not specifiedPlanned / design
Priority Power Management, LLC
Oct 28, 2026
Cologix COL1 Columbus Data CenterSite · Connected record
Columbus, Ohio, United States
Cologix, Inc.
Operating
Not establishedIn published records
Cologix, Inc.
Oct 28, 2026
Cologix COL2 Columbus Data CenterSite · Connected record
Columbus, Ohio, United States
Cologix, Inc.
Operating
Not establishedIn published records
Cologix, Inc.
Oct 28, 2026
Cologix COL3 Columbus Data CenterSite · Connected record
Columbus, Ohio, United States
AEP OhioCologix, Inc.
Operating
More than 18 MW
Basis: Basis not specifiedFacility design
Cologix, Inc.
Oct 28, 2026
Cologix COL4 Columbus Data CenterSite · Connected record
Columbus, Ohio, United States
Cologix, Inc.
Operating
40 MW
Basis: Basis not specifiedFacility design
Cologix, Inc.
Oct 28, 2026
Cologix JAX2 Jacksonville Data CenterSite · Connected record
Jacksonville, Florida, United States
Cologix, Inc.
Operating
Not establishedIn published records
Cologix, Inc.
Oct 28, 2026
Cologix Johnstown AI Data Center CampusSite · Connected record
Johnstown, Ohio, United States
Cologix, Inc.
Preconstruction
800 MW
Basis: Basis not specifiedPlanned / design
Cologix, Inc.
Oct 28, 2026
Cologix MIN2 Minneapolis Data CenterSite · Connected record
Minneapolis, Minnesota, United States
Cologix, Inc.
Operating
Not establishedIn published records
Cologix, Inc.
Oct 28, 2026
Cologix MIN3 Minneapolis Data CenterSite · Connected record
Minneapolis, Minnesota, United States
Cologix, Inc.
Operating
Not establishedIn published records
Cologix, Inc.
Oct 28, 2026
Columbus Georgia Data CenterSite · Connected record
Columbus, Georgia, United States
Georgia Data CenterHabitat Real Estate Partners
Proposed
600 MW
Basis: Basis not specifiedPlanned / design
Georgia Data Center
Oct 28, 2026
Compass Goodyear Data Center CampusSite · Connected record
Goodyear, Arizona, United States
Compass Datacenters
Operating
212 MW
Basis: Basis not specifiedPlanned / design
Compass Datacenters
Oct 28, 2026
Compass Meridian CampusSite · Connected record
Meridian, Mississippi, United States
Compass Datacenters
Construction
320 MW
Basis: Critical ITPlanned critical IT
Compass Datacenters
Oct 28, 2026
Compass Prince William Campus 1Site · Connected record
Gainesville, Virginia, United States
Compass DatacentersH&H Capital Acquisitions
Status under review
Not establishedIn published records
Compass Datacenters
Oct 28, 2026
Compass Statesville Data CenterSite · Connected record
Statesville, North Carolina, United States
Compass Datacenters
Proposed
500 MW
Basis: Basis not specifiedPlanned / design
Compass Datacenters
Oct 28, 2026
Core Scientific Dalton 1 AI Data Center ConversionSite · Connected record
Dalton, Georgia, United States
Core Scientific, Inc.
Construction
30 MW
Basis: Basis not specifiedPlanned / design
Core Scientific, Inc.
Oct 28, 2026
Core Scientific Dalton 4 AI Data Center CampusSite · Connected record
Dalton, Georgia, United States
Core Scientific, Inc.
Construction
145 MW
Basis: Basis not specifiedPlanned / design
Core Scientific, Inc.
Oct 28, 2026
Core Scientific Denton 1 Data Center CampusSite · Connected record
Denton, Texas, United States
City of DentonCore Scientific, Inc.
Partially operational
394 MW
Basis: Critical ITPlanned critical IT
Core Scientific, Inc.
Oct 28, 2026
Core Scientific Pecos Data Center CampusSite · Connected record
Pecos / Cottonwood, Texas, United States
Core Scientific, Inc.Reeves County
Partially operational
300 MW
Basis: Basis not specifiedContracted
Core Scientific, Inc.
Oct 28, 2026
Core Scientific Port Muskogee HPC Data CenterSite · Connected record
Muskogee, Oklahoma, United States
Core Scientific, Inc.
Preconstruction
1,500 MW
Basis: Basis not specifiedPlanned / design
Core Scientific, Inc.
Oct 28, 2026
CoreSite CH2 Chicago Data CenterSite · Connected record
Chicago, Illinois, United States
CoreSite
Operating
18 MW
Basis: Basis not specifiedFacility design
CoreSite
Oct 28, 2026
CoreSite DE1 Denver Data CenterSite · Connected record
Denver, Colorado, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite DE2 Denver Data CenterSite · Connected record
Denver, Colorado, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite LA1 Los Angeles Data CenterSite · Connected record
Los Angeles, California, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite LA2 Los Angeles Data CenterSite · Connected record
Los Angeles, California, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite LA3 Los Angeles Data CenterSite · Connected record
Los Angeles, California, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite NY1 Manhattan Data CenterSite · Connected record
New York, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite NY2 Secaucus Data CenterSite · Connected record
Secaucus, New Jersey, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite SV3 Santa Clara Data CenterSite · Connected record
Santa Clara, California, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite SV4 Santa Clara Data CenterSite · Connected record
Santa Clara, California, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreSite SV5 Santa Clara Data CenterSite · Connected record
Santa Clara, California, United States
American Tower CorporationCoreSite
Operating
Not establishedIn published records
American Tower Corporation
Oct 28, 2026
CoreSite SV9 Santa Clara Data CenterSite · Connected record
Santa Clara, California, United States
CoreSite
Operating
34 MW
Basis: Basis not specifiedFacility design
CoreSite
Oct 28, 2026
CoreSite VA2 Reston Data CenterSite · Connected record
Reston, Virginia, United States
CoreSite
Operating
Not establishedIn published records
CoreSite
Oct 28, 2026
CoreWeave Kenilworth AI Data Center CampusSite · Connected record
Kenilworth, New Jersey, United States
CoreWeaveCW Grosbeaks NEST Urban Renewal LLC
Construction
100 MW
Basis: Basis not specifiedPlanned / design
CoreWeave
Oct 28, 2026
CoreWeave Lancaster AI Data CenterSite · Connected record
Lancaster area, Pennsylvania, United States
Chirisa Technology ParksCoreWeave
Preconstruction
100 MW
Basis: Basis not specifiedPlanned / design
Chirisa Technology Parks
Oct 28, 2026
CoreWeave Plano AI Data CenterSite · Connected record
Plano, Texas, United States
CoreWeave, Inc.
Operating
Not establishedIn published records
CoreWeave, Inc.
Oct 28, 2026
Crow Holdings Fayetteville Data Center ProposalSite · Connected record
Highway 85 North, north of Fayette Pavilion, Georgia, United States
CHI/Acquisitions, LPCity of Fayetteville
Cancelled
Not establishedIn published records
CHI/Acquisitions, LP
Oct 28, 2026
Crow Holdings–CleanArc Central Dallas CampusSite · Connected record
Stemmons Corridor, central Dallas, Texas, United States
CleanArc Data CentersCrow Holdings
Preconstruction
245 MW
Basis: Basis not specifiedPlanned / design
CleanArc Data Centers
Oct 28, 2026
Crow Holdings–CleanArc Stemmons Data Center CampusSite · Connected record
Dallas, Texas, United States
CleanArc Data CentersCrow Holdings
Preconstruction
245 MW
Basis: Basis not specifiedPlanned / design
CleanArc Data Centers
Oct 28, 2026
Crusoe Port of Victoria CampusSite · Connected record
Victoria, Texas, United States
Crusoe
Proposed
Not establishedIn published records
Crusoe
Oct 28, 2026
Crusoe Tallgrass WyomingSite · Connected record
Cheyenne, Wyoming, United States
CrusoeGoogle
Delayed
Not establishedIn published records
Crusoe
Oct 28, 2026

Every figure carries its capacity stage. Operating, contracted, planned/design and utility-service values remain distinct; generation is never used as site capacity. A missing figure does not mean zero; other scoped figures may appear in the profile.