CoreWeave Kenilworth AI Data Center Campus

Kenilworth, New Jersey, United StatesUnder construction
Evidence
Planned / design
100 MW
Updated
Oct 28, 2026
Utility
Public Service Electric & Gas

CoreWeave's current Kenilworth project page, checked October 28, 2026, describes approximately $150 million of electrical infrastructure investment, including a new substation serving NEST 11 and the surrounding community. This is not the site's total construction cost or evidence that the adjacent potential 100 MW expansion has started or opened. CoreWeave-controlled portion of NEST: NEST 11 conversion plus adjacent expansion land; not the entire former Merck/NEST campus. CoreWeave Kenilworth AI Data Center Campus is in Kenilworth, NJ, US and is a data center campus with under construction status.

Capacity

Nest11 reported existing capacity

Planned / design or future potential

42 MW

Source

Adjacent future expansion capacity

Planned / design or future potential

100 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

NEST 11 conversion and expansion within qualified facilityUnder construction

1 building

Current NJEDA scope is 392,600 square feet: 284,500 rehabilitation plus 108,100 new construction.

Adjacent 27-acre future expansionPlanned

Future ground-up expansion; separate from NEST 11 and the 50 MW host-campus substation.

Milestones (8)
CoreWeave announces lease of NEST 11

Oct 28, 2024 · Recorded actual event

Completed · Event type not stated

Source not linked
Planning Board approves substation application

Apr 24, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
Planning Board approves CoreWeave data center site plan

May 15, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
CoreWeave acquires NEST 11 and adjacent land

Aug 1, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
NJEDA records construction start

Sep 15, 2025 · Recorded actual event

Completed · Construction started

Source not linked
NJEDA approves Next New Jersey AI tax-credit award

Nov 12, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
Planning Board considers major subdivision

Apr 28, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
Subdivision resolution appears on Planning Board agenda

Jun 23, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked

Participants

CoreWeave

Developer · Operator

Sources by role
Developer / Operator (1)
Developer / Operator (1)
CW NEST Tenant LLC

Tenant

Sources by role
Tenant (1)
Other participants (3)
Kenilworth Planning Board

Government authority

Sources by role
Government authority (1)
Government authority (1)
New Jersey Economic Development Authority

Government authority

Sources by role
Government authority (1)
Public Service Electric & Gas

Utility provider

Sources by role
Utility provider (1)
Utility provider (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Eligible capital investment

Actual

$1,757,842,000

Source

Next nj tax credit award

Actual

$250 million

Source

Real estate acquisition price

Actual

$322 million

Source

Financing records

Real estate acquisition consideration

$322m

Aug 1, 2025

Purchase of NEST 11 and adjacent 27 acres; separate from construction capex and tax credit.

Parties & sources

CoreWeave (Buyer; affiliate ownership structure) · Machine Investment Group (Seller; former landlord) · Newmark (Seller broker) · Onyx Equities (Seller; former landlord)

Incentives

Incentive

for 5 years

Status not stated · New Jersey Economic Development Authority

USD50 million per year for first five years, USD250 million total, conditioned on ten-year New Jersey commitment and program compliance.

Site & development

Current project area

Actual

392,600 square feet

Source

Renovation area

Actual

284,500 square feet

Source

New construction area

Actual

108,100 square feet

Source

Construction start

Actual

2025-09-15

Source

Technical specifications

Water tank count

Actual

4 tanks

Source

Additional project facts

Affiliate lease term

Actual

15 years

Source

New full time jobs

Actual

143 jobs

Source

Backup generator count

Actual

31 generators

Source

Chiller count

Actual

29 chillers

Source

Major subdivision is capacity event

Source report

False

Source

Infrastructure & permits

Technical details (3)
Electric grid

Secured or contracted

50 MW

Former NEST host-campus substation context; not full CoreWeave allocation.

Onsite generation

Secured or contracted

31 generators

Standby-generator field for NEST 11; emissions permits and ratings remain open.

Cooling system

Secured or contracted

29 chillers

Chiller yard with 29 units and four water tanks.

Permit · Issued

PSE&G-operated substation

Kenilworth Planning Board

Apr 24, 2025

Sources (1)
Permit · Issued

NEST 11 data center

Kenilworth Planning Board

May 15, 2025

Sources (1)
Permit · Status not stated

CoreWeave-controlled NEST parcel

Kenilworth Planning Board

Jun 23, 2026

Sources (2)

Public-source research. Plans may change. See Evidence for sources and qualifications.