CoreWeave Kenilworth AI Data Center Campus
- Planned / design
- 100 MW
- Updated
- Oct 28, 2026
- Utility
- Public Service Electric & Gas
CoreWeave's current Kenilworth project page, checked October 28, 2026, describes approximately $150 million of electrical infrastructure investment, including a new substation serving NEST 11 and the surrounding community. This is not the site's total construction cost or evidence that the adjacent potential 100 MW expansion has started or opened. CoreWeave-controlled portion of NEST: NEST 11 conversion plus adjacent expansion land; not the entire former Merck/NEST campus. CoreWeave Kenilworth AI Data Center Campus is in Kenilworth, NJ, US and is a data center campus with under construction status.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Current NJEDA scope is 392,600 square feet: 284,500 rehabilitation plus 108,100 new construction.
Future ground-up expansion; separate from NEST 11 and the 50 MW host-campus substation.
Milestones (8)
Oct 28, 2024 · Recorded actual event
Completed · Event type not stated
Source not linkedApr 24, 2025 · Recorded actual event
Completed · Event type not stated
Source not linkedMay 15, 2025 · Recorded actual event
Completed · Event type not stated
Source not linkedAug 1, 2025 · Recorded actual event
Completed · Event type not stated
Source not linkedSep 15, 2025 · Recorded actual event
Completed · Construction started
Source not linkedNov 12, 2025 · Recorded actual event
Completed · Event type not stated
Source not linkedApr 28, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedJun 23, 2026 · Recorded actual event
Completed · Event type not stated
Source not linkedParticipants
Developer · Operator
Sources by role
Developer / Operator (1)
- NJEDA Board Book — CoreWeave Next New Jersey AI award · Nov 12, 2025 · Primary
Developer / Operator (1)
- Kenilworth Planning Board minutes — CoreWeave data center application 25-003 · May 15, 2025 · Corroborating
Developer
Sources by role
Developer (1)
- Kenilworth Planning Board agenda — CoreWeave subdivision resolution · Jun 23, 2026 · Corroborating
Developer (1)
- Kenilworth Planning Board agenda — CoreWeave major subdivision · Apr 28, 2026 · Primary
Tenant
Sources by role
Tenant (1)
- NJEDA Board Book — CoreWeave Next New Jersey AI award · Nov 12, 2025 · Primary
Other participants (3)
Government authority
Sources by role
Government authority (1)
- Kenilworth Planning Board minutes — CoreWeave data center application 25-003 · May 15, 2025 · Primary
Government authority (1)
- Kenilworth Planning Board minutes — substation application 25-004 · Apr 24, 2025 · Corroborating
Government authority
Sources by role
Government authority (1)
- NJEDA Board Book — CoreWeave Next New Jersey AI award · Nov 12, 2025 · Primary
Utility provider
Sources by role
Utility provider (1)
- Kenilworth Planning Board minutes — substation application 25-004 · Apr 24, 2025 · Primary
Utility provider (1)
- CoreWeave signs 280,000-square-foot lease at NEST · Oct 28, 2024 · Corroborating
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Real estate acquisition consideration
$322mAug 1, 2025
Purchase of NEST 11 and adjacent 27 acres; separate from construction capex and tax credit.
Parties & sources
CoreWeave (Buyer; affiliate ownership structure) · Machine Investment Group (Seller; former landlord) · Newmark (Seller broker) · Onyx Equities (Seller; former landlord)
Sources (2)
Incentives
Incentive
for 5 years
Status not stated · New Jersey Economic Development Authority
USD50 million per year for first five years, USD250 million total, conditioned on ten-year New Jersey commitment and program compliance.
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (3)
Secured or contracted
50 MW
Former NEST host-campus substation context; not full CoreWeave allocation.
Secured or contracted
31 generators
Standby-generator field for NEST 11; emissions permits and ratings remain open.
Secured or contracted
29 chillers
Chiller yard with 29 units and four water tanks.
Project map
Permit · Issued
PSE&G-operated substation
Kenilworth Planning Board
Apr 24, 2025
Sources (1)
- Kenilworth Planning Board minutes — substation application 25-004 · Apr 24, 2025 · Primary
Permit · Issued
NEST 11 data center
Kenilworth Planning Board
May 15, 2025
Sources (1)
- Kenilworth Planning Board minutes — CoreWeave data center application 25-003 · May 15, 2025 · Primary
Permit · Status not stated
CoreWeave-controlled NEST parcel
Kenilworth Planning Board
Jun 23, 2026
Sources (2)
- Kenilworth Planning Board agenda — CoreWeave subdivision resolution · Jun 23, 2026 · Corroborating
- Kenilworth Planning Board agenda — CoreWeave major subdivision · Apr 28, 2026 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.