Skip to content

Crow Holdings Fayetteville Data Center Proposal

Highway 85 North, north of Fayette Pavilion, Georgia, United StatesCancelled
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Crow Holdings Development and CHI/Acquisitions proposed a single data center building north of Fayette Pavilion. The Planning & Zoning Commission denied the site plan, the applicants withdrew their appeal, and Fayetteville now prohibits new data centers in every zoning district.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Site plan and appealChanged or cancelled

1 building

Cancelled entitlement path for one proposed two-story data center building and a substation.

Milestones (3)
Planning commission denies proposal

Jan 27, 2026 · Event timing type not established

Cancelled · Permit approved

Source not linked
Fayetteville adopts citywide prohibition

Mar 5, 2026 · Recorded actual event

Completed · Permit approved

Source not linked
Developer withdraws appeal

Mar 18, 2026 · Recorded actual event

Completed · Cancelled

Source not linked

Participants

CHI/Acquisitions, LP

Developer

Sources by role
Crow Holdings Development

Developer

Sources by role
Other participants (2)
City of Fayetteville

Government authority

Sources by role
Government authority (1)
Fayetteville Planning & Zoning Commission

Government authority

Sources by role
Government authority (1)

Site & development

Location

Proposal

North of Fayette Pavilion along Highway 85 North, Fayetteville, Georgia

Source

Site area

Proposal

37.4 acres

Source

Building area

Proposal

300,000 sq. ft.

Source

Building count

Proposal

1 two story building

Source

Site plan decision

Actual

Denied by Planning & Zoning Commission

Site plan and appeal · Phase

Source

Additional project facts

Substation

Proposal

One proposed substation

Source

Appeal status

Actual

Officially withdrawn

Site plan and appeal · Phase

Source

Zoning context

Permitted

New data centers prohibited in every City of Fayetteville zoning district

Source

Cryptomining use

Proposal

Prohibited in supporting documentation

Source

Current status

Actual

Cancelled after denial and appeal withdrawal

Source

Boundary exclusion

Actual

Distinct from the operating QTS Fayetteville campus on Highway 54 West

Source

Infrastructure & permits

Technical details (1)
Electric grid

Cancelled or not proceeding

Concept plan reportedly included a substation; utility, capacity and interconnection were not disclosed.

Other · Denied

Crow Holdings Fayetteville proposal

Fayetteville Planning & Zoning Commission

Jan 27, 2026

Sources (1)
Other · Denied

Citywide data center use

City of Fayetteville

Mar 5, 2026

Sources (1)
Other · Withdrawn

Crow Holdings Fayetteville proposal

City of Fayetteville

Mar 18, 2026

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.