The Columbus, Georgia proposal is publicly known as Project Ruby and is being advanced by Habitat Real Estate Partners through Muscogee Property 1 LLC. The concept covers about 865 acres, shows four buildings, seeks power delivery in three 200 MW tranches from 2029 to 2034, and has not yet received site rezoning or development permits.

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Future Potential600 MWDesign · Columbus Georgia Data Center

Development

1 phases · 3 milestones
Concept and zoning-framework developmentAnnounced Or Preconstruction

The Columbus, Georgia proposal is publicly known as Project Ruby and is being advanced by Habitat Real Estate Partners through Muscogee Property 1 LLC. The concept covers about 865 acres, shows four buildings, seeks power delivery in three 200 MW tranches from 2029 to 2034, and has not yet received site rezoning or development permits.

4 buildings

Feb 24, 2026
Project presented to Columbus Council
Completed
Jan 1, 2029
Target first 200 MW tranche
Forecast
Dec 31, 2034
Target full 600 MW request
Forecast

Infrastructure

Electric GridPotential Or Planned

600 MW

Feasibility request in three 200 MW tranches; no service contract or operating load.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
Columbus Georgia Data Center | Columbus | Georgia | US
Actual
Lifecycle Status
Proposed
Actual
Reported Capacity
600 MW
Design
Capacity Basis
600 MW future full build site capacity; not measured operating IT load.
Actual
Public Project Name
Project Ruby
Actual
Developer
Habitat Real Estate Partners
Actual
Site Area
865 acres
Reported Rounded
Building Count
4