Core Scientific Dalton 1 AI Data Center Conversion

Dalton, Georgia, United StatesUnder construction
Capacity
30 MW
Planned / design
Lead participant
Core Scientific, Inc.
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Core Scientific Dalton 1 AI Data Center Conversion

Core Scientific is converting its Dalton 1 facility from cryptocurrency mining to AI and HPC workloads. The planned converted data center is sized for 30 MW. Core Scientific is publicly identified in the project record for Dalton, Whitfield County, GA, US. The disclosed development record includes 30 MW planned conversion; existing one-building campus; approximately five-acre site. Power and infrastructure include brownfield conversion of an existing powered data center building for high-density workloads. Core Scientific states Dalton 1 will feature a 30 MW converted data center.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design30 MWDesign · Core Scientific Dalton 1 AI Data Center Conversion

Development

1 phases · 2 milestones
Construction programUnder Construction

Project-wide phase for Core Scientific Dalton 1 AI Data Center Conversion; capacity remains classified as design.

Apr 24, 2026
Dalton 1 project status and capacity disclosed
Completed
Existing facility conversion to AI and HPC use
Forecast

Infrastructure

Electric GridPlanned Or Represented

30 MW

Core Scientific states Dalton 1 will feature a 30 MW converted data center.

Site FacilityPlanned Or Represented

Brownfield conversion of an existing powered data center building for high-density workloads.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
2205 Industrial South Road | Dalton | Georgia
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
30 MW
Design
Capacity Basis
Core Scientific states Dalton 1 will feature a 30 MW converted data center.
Actual
Development Scale
30 MW planned conversion
Actual
Development Milestone
Existing one building campus
Actual
Power Arrangement
Approximately five acre site.
Actual
Boundary Context
2205 Industrial South Road | Dalton | Georgia