Compass Meridian Campus
- Planned critical IT
- 320 MW
- Updated
- Oct 28, 2026
Compass broke ground in 2025 on an eight-building data center campus in Meridian, Mississippi. Each building is designed for 40 MW of critical IT load, producing a planned campus total of 320 MW. The approximately $10 billion development is supported by Mississippi Power and state and local development programs.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Compass Meridian Campus: Construction program.
Milestones (2)
Date not disclosed · Event timing type not established
In progress · Construction started
Source not linkedDate not disclosed · Event timing type not established
In progress · Status changed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Compass data center markets — Meridian · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Infrastructure
ActualThe approximately $10 billion development is supported by Mississippi Power and state and local development programs.
SourceFinancing records
Investment commitment
$10bnMay 12, 2025
Announced campus investment.
Parties & sources
Compass Datacenters (Sponsor)
Sources (2)
Site & development
Development scale
ActualCompass broke ground in 2025 on an eight building data center campus in Meridian, Mississippi. Each building is designed for 40 MW of critical IT load, producing a planned campus total of 320 MW
SourceAdditional project facts
Infrastructure & permits
Technical details (2)
Planned or represented
320 MW
320 MW planned critical IT design capacity
Planned or represented
The approximately $10 billion development is supported by Mississippi Power and state and local development programs.