Crow Holdings–CleanArc Central Dallas Campus

Stemmons Corridor, central Dallas, Texas, United StatesPreconstruction
Evidence
Planned / design
245 MW
Updated
Oct 28, 2026

Crow Holdings and CleanArc announced a multi-building data center campus on roughly 40 acres in central Dallas. The plan allows up to 245 MW, while the first 70 MW building is targeted for late 2027.

Capacity

Campus power envelope

Planned / design or future potential

245 MW

Source

Phase power envelope

Planned / design or future potential

70 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Phase I — first buildingPlanned

1 building

Turnkey power figure and target date; no start or energization verified.

Full campus buildoutPlanned

Full design envelope supported by a dedicated on-site substation concept.

Milestones (2)
Crow announces 245 MW campus and first 70 MW building

Jan 20, 2026 · Recorded actual event

Completed · Announced

Source not linked
First 70 MW building target

Q4 2027 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Site & development

Site area

Reported rounded

40 acres

Source

Building configuration

Actual

Multi building campus

Source

Site ownership history

Actual

Owned by Crow Holdings for decades

Source

Location context

Actual

Stemmons Corridor, central Dallas

Source

Additional project facts

Announcement status

Actual

Announced

Source

Phase target rfs

Forecast

Late 2027

Source

Substation plan

Design

Dedicated on site substation

Source

Infrastructure & permits

Technical details (3)
Electric grid

Planned or represented

245 MW

Full multi-building turnkey campus envelope; not operating IT load.

Electric grid

Planned or represented

70 MW

First-building turnkey figure targeted for late 2027.

Electric grid

Planned or represented

Dedicated on-site substation concept; utility, voltage and interconnection status undisclosed.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
Crow Holdings–CleanArc Stemmons Data Center Campus

Preconstruction · Dallas, Texas, United States

Shared participant: CleanArc Data Centers · Shared participant: Crow Holdings · Same market: Texas, United States

Compare in a collection