Cloverleaf Infrastructure Troy Campus

Troy, Illinois, United StatesProposed
Evidence
Planned / design
500 MW
Updated
Oct 28, 2026

Troy’s February 2, 2026 council minutes record the mayor’s statement that the original Route 162/US 40 site was off the table and a southern alternative was again being explored. This is a site-specific change, not approval of a replacement site or cancellation of all potential development in Troy. Cloverleaf’s Project Beacon was initially presented as a proposed 500 MW data center campus in Troy, Illinois. The earlier concept plans showed either a six-building Phase 1 on about 165 acres or a four-building full-build layout on roughly 275 acres; no formal application had been filed when the project was first presented, and zoning and utility approvals remain required.

Capacity

Reported capacity

Planned / design or future potential

500 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Pre-application community reviewAnnounced or preconstruction

Cloverleaf’s Project Beacon is a proposed 500 MW data center campus in Troy, Illinois. Concept plans show either a six-building Phase 1 on about 165 acres or a four-building full-build layout on roughly 275 acres; no formal application had been filed when the project was first presented, and zoning and utility approvals remain required.

Milestones (2)
Cloverleaf held initial informational meeting

Jan 8, 2026 · Recorded actual event

Completed · Announced

Source not linked
Project Beacon question-and-answer session held

Feb 10, 2026 · Recorded actual event

Completed · Announced

Source not linked

Participants

Cloverleaf Infrastructure

Developer

Sources by role

Site & development

Location context

Actual

Cloverleaf Infrastructure Troy Campus | Troy | Illinois | US

Source

Full build site area

Reported rounded

275 acres

Source

Phase one buildings

Reported rounded

6 buildings

Source

Additional project facts

Lifecycle status

Actual

Proposed

Source

Capacity basis

Actual

500 MW future full build site capacity; not measured operating IT load.

Source

Public project name

Actual

Project Beacon

Source

Infrastructure & permits

Technical details (1)
Electric grid

Potential or planned

500 MW

Ameren/MISO approvals and customer-funded upgrades required.

Other · Documented

Project Beacon

City of Troy

Jan 27, 2026

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.