Data center siteSite record

Core Scientific Denton 1 Data Center Campus

Denton, Texas, United StatesPartially operational
Capacity
394 MW
Planned critical IT
Lead participant
Core Scientific, Inc.
Operator
Last updated
Aug 24, 2026
Most recent public record update

About Core Scientific Denton 1 Data Center Campus

Core Scientific is converting and expanding its established Denton campus for phased CoreWeave HPC delivery while some campus capacity has already begun generating colocation revenue. Participants include Core Scientific, Inc. as operator, CoreWeave, Inc. as customer, City of Denton as landowner, Denton Municipal Electric as utility provider. Published specifications include 394 MW operating it capacity, 260 MW planned capacity. Development comprises Historical bitcoin-mining operations (operational), CoreWeave HPC conversion and initial delivery (operational), Additional 70-MW CoreWeave expansion (construction). Key milestones include Denton data halls completed in Q2 and Q3. (2025-09-30) and Incremental billable capacity reported. (2026-03-31). municipal grid service — 394 MW_site_envelope: Amended Denton power arrangement;. emergency backup generation — 22 generator_units_reported: Secondary report described 22 generators; reconcile with TCEQ equipment records. Permitting includes permit by rule registration for Core Scientific Site 1 and 2 (correspondence issued). Capital records include hosting contract incremental revenue of 1200000000 USD for Incremental contracted revenue for additional 70 MW; commercial contract, not capex financing.

Projects sharing a market, utility, or organization.

3 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load394 MWFact · Core Scientific Denton 1 Data Center Campus
Future Potential260 MWFact · Core Scientific Denton 1 Data Center Campus

Development

3 phases · 5 milestones
Historical bitcoin-mining operationsOperational

125 MW operating baseline reported in April 2024; remaining mining allocation at cutoff unresolved.

CoreWeave HPC conversion and initial deliveryOperational

Denton data halls completed in Q2 and Q3 2025; delivered MW requires reconciliation.

Additional 70-MW CoreWeave expansionUnder Construction

Raises planned CoreWeave critical IT capacity at Denton to approximately 260 MW.

Apr 16, 2024
Mining expansion baseline announced
Completed
Nov 20, 2024
Denton approves lease and power expansion
Completed
Feb 26, 2025
Additional 70-MW CoreWeave expansion announced
Completed
Sep 30, 2025
Denton data halls completed in Q2 and Q3
Completed
Mar 31, 2026
Incremental billable capacity reported
Completed

Infrastructure

Electric GridSecured Or Contracted

394 MW site envelope

Amended Denton power arrangement;.

Onsite GenerationSecured Or Contracted

22 generator units reported

Secondary report described 22 generators; reconcile with TCEQ equipment records.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
2

No map point available

Power & interconnection: 1Generation & storage: 1

Facts & sources

Published claims and their source links.

8 facts
Site Power Envelope
394 MW
Fact
Coreweave Critical It Capacity Planned
260 MW
Fact
Site Area
78 acres
Actual
Floor Area
423,831 sq. ft.
Actual
Projected Real Property Investment
$6,100,000,000
Fact
Incremental Contracted Revenue
$1,200,000,000
Fact
Data Halls Completed
Q2 and Q3 2025
Actual
Incremental Billable Capacity
Achieved Q1 2026
Actual