Cipher Ulysses AI Data Center Campus

Ohio, United StatesPreconstruction
Capacity
200 MW
Utility capacity
Lead participant
Cipher Digital
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Cipher Ulysses AI Data Center Campus

Cipher is preparing Ulysses as a 200 MW gross-power HPC campus in Ohio. Interconnection is approved and substation work has begun, while tenant discussions remain ongoing. Cipher Digital is publicly identified in the project record for Ohio location undisclosed, OH, US. The disclosed development record includes 200 MW gross capacity; interconnection approved; substation development initiated; target energization Q4 2027. Power and infrastructure include approved grid interconnection and new substation for an HPC campus. Cipher reports 200 MW gross capacity with approved interconnection.

Capacity

Utility capacity
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Utility Service200 MWDesign · Cipher Ulysses AI Data Center Campus

Development

1 phases · 2 milestones
Development programAnnounced Or Preconstruction

Project-wide phase for Cipher Ulysses AI Data Center Campus; capacity remains classified as utility service.

Aug 10, 2026
Ulysses project status and capacity disclosed
Completed
Interconnection approved and substation development initiated
Forecast

Infrastructure

Electric GridPlanned Or Represented

200 MW

Cipher reports 200 MW gross capacity with approved interconnection.

Site FacilityPlanned Or Represented

Approved grid interconnection and new substation for an HPC campus.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
Ulysses campus | Ohio | precise boundary undisclosed
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
200 MW
Design
Capacity Basis
Cipher reports 200 MW gross capacity with approved interconnection.
Actual
Development Scale
200 MW gross capacity
Actual
Development Milestone
Interconnection approved
Actual
Power Arrangement
Substation development initiated
Actual
Site Configuration
Target energization Q4 2027.
Actual