Data center siteSite record

Cipher Reveille AI Data Center Campus

Texas, United StatesPreconstruction
Capacity
70 MW
Utility capacity
Lead participant
Cipher Digital
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Cipher Reveille AI Data Center Campus

Cipher is preparing Reveille as a 70 MW gross-power HPC campus. Its ERCOT interconnection is approved and substation development has started, while tenant discussions continue. Cipher Digital is publicly identified in the project record for Texas location undisclosed, TX, US. The disclosed development record includes 70 MW gross capacity; ERCOT interconnection approved; substation development initiated; target energization Q3 2027. Power and infrastructure include approved ERCOT interconnection and planned data center substation. Cipher reports 70 MW gross capacity with approved ERCOT interconnection.

Projects sharing a market, utility, or organization.

4 related

Capacity

Utility capacity
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Utility Service70 MWDesign · Cipher Reveille AI Data Center Campus

Development

1 phases · 2 milestones
Development programAnnounced Or Preconstruction

Project-wide phase for Cipher Reveille AI Data Center Campus; capacity remains classified as utility service.

Aug 10, 2026
Reveille project status and capacity disclosed
Completed
Interconnection approved and substation development initiated
Forecast

Infrastructure

Electric GridPlanned Or Represented

70 MW

Cipher reports 70 MW gross capacity with approved ERCOT interconnection.

Site FacilityPlanned Or Represented

Approved ERCOT interconnection and planned data center substation.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
Reveille campus | Texas | precise boundary undisclosed
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
70 MW
Design
Capacity Basis
Cipher reports 70 MW gross capacity with approved ERCOT interconnection.
Actual
Development Scale
70 MW gross capacity
Actual
Development Milestone
ERCOT interconnection approved
Actual
Power Arrangement
Substation development initiated
Actual
Site Configuration
Target energization Q3 2027.
Actual