College Station 600-MW Data Center Proposal
- Planned / design
- 600 MW
- Updated
- Oct 28, 2026
College Station rejected the proposed sale of approximately 200 acres in Midtown Business Park to Priority Power Management after reviewing a conceptual data center plan of up to 600 MW.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
2 buildings
Potential configuration only; building count and size remained dependent on power study.
Ends the identified proposal but is not a permit denial or land conveyance.
Milestones (2)
Sep 11, 2025 · Recorded actual event
Completed · Permit filed
Source not linkedSep 11, 2025 · Recorded actual event
Completed · Cancelled
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- September 11, 2025 City Council minutes in September 25 agenda packet · Sep 25, 2025 · Primary
Developer (1)
- September 11, 2025 Regular Agenda Packet — City Council · Sep 11, 2025 · Corroborating
Other participants (1)
Government authority
Sources by role
Government authority (1)
- September 11, 2025 City Council minutes in September 25 agenda packet · Sep 25, 2025 · Primary
Government authority (1)
- September 11, 2025 Regular Agenda Packet — City Council · Sep 11, 2025 · Corroborating
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Commercial contract
$30mSep 11, 2025
Reported total price for an approximately 200-acre contract that was denied; not financing or closed transaction.
Parties & sources
City of College Station (Other) · Priority Power Management, LLC (Other)
Site & development
Technical specifications
Additional project facts
Alternate configuration
Proposal2–3 Story project or multiple data centers
Midtown Business Park contingent land-sale proposal · Phase
Conflicting public evidence
SourceInfrastructure & permits
Technical details (3)
Cancelled or not proceeding
600 MW
Potential campus figure subject to a power study; basis is not identified as IT load.
Cancelled or not proceeding
Available electrical capacity was unresolved when the contract was denied.
Cancelled or not proceeding
Additional agreements would have been required; no service entitlement imported.
Project map
Other · Denied
Midtown Business Park contingent land sale
City of College Station
Sep 11, 2025
Sources (1)
- September 11, 2025 City Council minutes in September 25 agenda packet · Sep 25, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.