All records
Data center siteSite record
College Station 600-MW Data Center Proposal
College Station, Texas, United StatesCancelled
Capacity
600 MW
Planned / design
Lead participant
Priority Power Management, LLC
Developer
Last updated
Aug 22, 2026
Most recent public record update
About College Station 600-MW Data Center Proposal
College Station rejected the proposed sale of approximately 200 acres in Midtown Business Park to Priority Power Management after reviewing a conceptual data center plan of up to 600 MW.
Capacity
Planned / designOperating capacity—An operating IT-capacity figure has not been publicly disclosed.
Future Potential600 MWDesign · College Station 600-MW Data Center Proposal
Development
2 phases · 2 milestonesMidtown Business Park contingent land sale proposalAnnounced Or Preconstruction
Potential configuration only; building count and size remained dependent on power study.
2 buildings
City Council land-contract decisionChanged Or Cancelled
Ends the identified proposal but is not a permit denial or land conveyance.
Sep 11, 2025
Council considers Midtown Business Park contract and concept
CompletedSep 11, 2025
City Council unanimously denies land sale contract
CompletedInfrastructure
Electric GridCancelled Or Not Proceeding
600 MW
Potential campus figure subject to a power study; basis is not identified as IT load.
Electric GridCancelled Or Not Proceeding
Available electrical capacity was unresolved when the contract was denied.
Utility ServiceCancelled Or Not Proceeding
Additional agreements would have been required; no service entitlement imported.
Project map
0 of 1 project point mappedInfrastructure facts
3
Mapped records
1
Capacity figures
1
No map point available
Power & interconnection: 3
Facts & sources
Published claims and their source links.
Current StatusLand sale contract denied unanimouslyActual
Land sale contract denied unanimously
Proposed Land Area200 acresProposal
200 acres
Proposed Land Price Per Acre$150,000 per acreActual
$150,000 per acre
Reported Total Land Value$30,000,000Transaction Scope
$30,000,000
Potential Facility Capacity600 MWDesign
600 MW
Conceptual Building Count2Design
2
Sources report a conflicting figure.
Alternate Configuration2–3 Story project or multiple data centersProposal
2–3 Story project or multiple data centers
Sources report a conflicting figure.
Power Study StatusRequired and incompleteProposal
Required and incomplete
Water And Power AgreementsAdditional agreements requiredProposal
Additional agreements required
Projected Annual City Revenue$10,000,000–$22,000,000 per yearForecast
$10,000,000–$22,000,000 per year
Projected Operational Jobs45 jobsForecast
45 jobs
Projected Construction Jobs2,500 jobsForecast
2,500 jobs
Decision ScopeReal estate contract onlyActual
Real estate contract only