Search property-level records across markets, participants, capacity, development activity, infrastructure and supporting evidence.

970 site records69 program records1022 fully connected17 sourced research records

Site and program directory

Search markets, owners, developers, operators, utilities and connected organizations.

25 results · 50 per page
Tract Buckeye Technology ParkReviewed site record
Buckeye, Arizona, United States
Tract
Preconstruction
1,800 MW
Planned / design
Tract
Aug 27, 2026
Vermaland La Osa Data Center CampusReviewed site record
Pinal, Arizona, United States
Vermaland
Proposed
1,000 MW
Planned / design
Vermaland
Aug 28, 2026
QTS Phoenix 3 CampusReviewed site record
Glendale, Arizona, United States
QTS Data Centers
Preconstruction
750 MW
Planned / design
QTS Data Centers
Aug 30, 2026
EdgeCore Florence Tech ParkReviewed site record
Florence, Arizona, United States
EdgeCore
Proposed
720 MW
Planned / design
EdgeCore
Aug 28, 2026
Project BlueReviewed site record
Tucson, Arizona, United States
Beale Infrastructure
Preconstruction
600 MW
Planned / design
Beale Infrastructure
Aug 28, 2026
EdgeCore Mesa Data Center CampusReviewed site record
Mesa, Arizona, United States
EdgeCore Digital Infrastructure
Under construction
496 MW
Planned critical IT
EdgeCore Digital Infrastructure
Aug 27, 2026
QTS Phoenix DC1 40th Street Data Center CampusReviewed site record
Phoenix, Arizona, United States
QTS Data Centers
Partially operational
280 MW
Planned critical IT
QTS Data Centers
Aug 29, 2026
STACK PHX02 Central Phoenix Data Center CampusReviewed site record
Phoenix, Arizona, United States
STACK Infrastructure
Preconstruction
250 MW
Planned critical IT
STACK Infrastructure
Aug 28, 2026
NTT Phoenix Elliot Road CampusReviewed site record
Mesa, Arizona, United States
NTT DATA
Partially operational
240 MW
Planned critical IT
NTT DATA
Aug 26, 2026
Prime Phoenix Campus PHX01Reviewed site record
Avondale, Arizona, United States
Prime Data Centers
Under construction
240 MW
Planned critical IT
Prime Data Centers
Aug 27, 2026
Prime PHX01 Avondale CampusReviewed site record
3700–3716 S. Avondale Boulevard, Avondale, Arizona, United States
ARCO/MurrayCity of Avondale
Under construction
240 MW
Planned critical IT
Prime Data Centers
Aug 22, 2026
STACK PHX01 Avondale Data Center CampusReviewed site record
Avondale, Arizona, United States
STACK Infrastructure
Preconstruction
225 MW
Planned / design
STACK Infrastructure
Aug 27, 2026
Compass Goodyear Data Center CampusReviewed site record
Goodyear, Arizona, United States
Compass Datacenters
Operating / Stabilized
212 MW
Planned / design
Compass Datacenters
Sep 1, 2026
Aligned Phoenix PHX01–PHX03 Data Center CampusReviewed site record
Phoenix, Arizona, United States
Aligned Data Centers
Partially operational
180 MW
Planned / design
Aligned Data Centers
Aug 28, 2026
Vantage Phoenix AZ1 GoodyearReviewed site record
45 South Bullard Avenue, Goodyear, Arizona, United States
Arizona Public ServiceCorgan
Partially operational
176 MW
Planned critical IT
Vantage Data Centers
Aug 25, 2026
CyrusOne PHX1–PHX8 Chandler Data Center CampusReviewed site record
Chandler, Arizona, United States
CyrusOne
Partially operational
169 MW
Planned / design
CyrusOne
Aug 30, 2026
Iron Mountain AZP-2 Phoenix Data CenterReviewed site record
Phoenix, Arizona, United States
Iron Mountain Data Centers
Partially operational
48 MW
Planned critical IT
Iron Mountain Data Centers
Aug 28, 2026
Iron Mountain AZP-1 Phoenix Data CenterReviewed site record
Phoenix, Arizona, United States
Iron Mountain Data Centers
Operating / Stabilized
41 MW
Planned critical IT
Iron Mountain Data Centers
Aug 28, 2026
Iron Mountain AZP-3 Phoenix Data CenterReviewed site record
Phoenix, Arizona, United States
Iron Mountain Data Centers
Operating / Stabilized
36 MW
Planned critical IT
Iron Mountain Data Centers
Aug 28, 2026
Iron Mountain AZS-1 Scottsdale Data CenterReviewed site record
Scottsdale, Arizona, United States
Iron Mountain Data Centers
Operating / Stabilized
5.8 MW
Planned critical IT
Iron Mountain Data Centers
Aug 28, 2026
EdgeConneX Phoenix Data CenterReviewed site record
Tempe, Arizona, United States
EdgeConneX
Operating / Stabilized
Not disclosed
EdgeConneX
Sep 2, 2026
Google Mesa Data Center CampusReviewed site record
Mesa / Elliot and Sossaman roads, Arizona, United States
Arizona Corporation CommissionCity of Mesa
Under construction
Not disclosed
Google
Aug 24, 2026
Hassayampa Ranch Data CenterReviewed site record
Buckeye, Arizona, United States
Arizona Land Consulting
Proposed
Not disclosed
Arizona Land Consulting
Aug 28, 2026
Microsoft Goodyear Data Center CampusReviewed site record
Goodyear, Arizona, United States
Microsoft
Operating / Stabilized
Not disclosed
Microsoft
Aug 27, 2026
Project Blue TucsonReviewed site record
Pima County, Arizona, United States
Beale InfrastructureHumphrey’s Peak Properties LLC
Under development
Not disclosed
Beale Infrastructure
Oct 15, 2025

Every figure carries its capacity stage. Operating, contracted, planned/design and utility-service values remain distinct; generation is never used as site capacity, and unsupported values remain undisclosed.