NTT Phoenix Elliot Road Campus
- Planned critical IT
- 240 MW
- Updated
- Oct 28, 2026
NTT's Elliot Road campus in Mesa currently lists PH1 and PH4 as Phoenix facilities, each with 36 MW of critical IT load. The 102-acre campus was planned for seven buildings and 240 MW when fully operational.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Six 6 MW vaults; exact ready-for-service date remains unresolved.
1 building
Current NTT product page; opening date remains unresolved.
7 buildings
Campus envelope, not current delivered IT load.
Milestones (2)
Aug 17, 2021 · Recorded actual event
Completed · Announced
Source not linkedQ1 2022 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Phoenix PH1 Data Center · Primary
Developer (1)
- Phoenix PH4 Data Center · Corroborating
Developer (1)
- Phoenix Data Centers · Corroborating
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (5)
Operational
36 MW
PH1 facility-specific current product metric.
Operational
36 MW
PH4 facility-specific current product metric.
Partially operational
240 MW
Seven-building campus capacity when fully operational; not current delivered total.
Operational
Current PH1/PH4 pages describe on-site substation and diverse power distribution.
Operational
Closed-loop cooling; not a zero-water claim.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (1)
Partially operational · Mesa, Arizona, United States
Same locality: Mesa