Prime Phoenix Campus PHX01

Avondale, Arizona, United StatesUnder construction
Capacity
240 MW
Planned critical IT
Lead participant
Prime Data Centers
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Prime Phoenix Campus PHX01

Prime Data Centers broke ground in May 2026 on the first three buildings of PHX01 in Avondale, Arizona. The five-building, 66.5-acre campus is designed for 240 MW of critical IT load and represents an announced investment of roughly $3 billion. SRP utility service and an on-site substation are planned.

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load240 MWDesign · Prime Phoenix Campus PHX01
It Load240 MWDesign · Prime Phoenix Campus PHX01
It Load240 MW planned critical IT design capacityActual · Prime Phoenix Campus PHX01

Development

1 phases · 2 milestones
Construction programUnder Construction

Prime Phoenix Campus PHX01: Construction program.

May 21, 2026
Prime Phoenix Campus PHX01 — Construction program
In Progress
Prime Data Centers broke ground in May 2026 on the first three buildings of PHX01 in Avondale, Arizona.
In Progress

Infrastructure

Electric GridPlanned Or Represented

240 MW

240 MW planned critical IT design capacity

Site FacilityPlanned Or Represented

SRP utility service and an on-site substation are planned.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Prime PHX01 campus | Avondale | Arizona | United States
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
240 MW
Design
Capacity Basis
Five building campus critical IT design
Actual
Project Identity
Prime Phoenix Campus PHX01
Actual
Lifecycle Status
Construction program
Actual
Location
Avondale, Maricopa County, AZ, US
Actual
Participant Roles
Prime Data Centers
Actual
Capacity
240 MW
Design
Capacity Basis
240 MW planned critical IT design capacity
Actual
Development Scale
Prime Data Centers broke ground in May 2026 on the first three buildings of PHX01 in Avondale, Arizona. The five building, 66.5-acre campus is designed for 240 MW of critical IT load and represents an announced investment of roughly $3 billion
Actual
Infrastructure
SRP utility service and an on site substation are planned.
Actual